Sample Report
(One of many Standard Report Formats that are included with IIR’s database tool.)






PROJECT REPORT
Project KWALE GRASSROOT MINERAL SAND MINE & PROCESSING PLANT
Industry Code 08 Metals & Minerals Project ID 84000011
TIV $137,000,000 Verification ID AF020502-01
Project SIC Prod 1099 Miscellaneous Metal Ores Mining
Plant SIC 1099 Miscellaneous Metal Ores Mining
Environmental Air (A) Land (L) Water (W) Research Date 05/May/2002
OWNER Tiomin Resources Incorporated Plant Kwale Mineral Sands
Address 1 Adlaide Street Suite 2410 Plant ID 1033377 Activity 01 Reports
City/State Toronto ON M5C 2V9 Unit Name  
Phone (416) 350-3779 Zone KE*01 County Coast
Contact Jean-Charles Potvin Location 60Km South Of Mombasa
Title President & CEO City/State Mombasa, Kenya
E-Mail N/A Phone 011 254 (1) 272256
DEVELOPER Tiomin Resources Incorporated SITE.REP
Address P O Box 1214 Address
City/State Ukunda, Kenya City/State
Phone 011 254 (254) 127-2256 Phone
Contact Robert Borst Contact
Title Project Director Title
E-Mail N/A E-Mail
PEC® Timing P2 PEC® Activity Owner Review of Issue (19)
Scope OWNER performs Owner Review of Issue for G-R Mineral Sand and Processing Plant. DETAILS: Construct Mine and Processing Plant to produce, 300,000 MT/yr, Ilmenite, 75,000 MT/yr Rutile, 37,000 MT/yr Zircon, and construct 10-14MW N/G-Fired Power plant plant. REQUIRES: Buildings, Silos, Magnetic Separator, Concentrator, Rotary Drier, 10MW N/G-Fired Turb/Gen, Condensers, Screen, Grinders, Stackers, Compressor (Gas & Air), Filters, Hoppers plus PLC's. ENVIRONMENTAL:(A) Dust Collect, (L) Liners; (W) Wastewater Treatment.
Schedule OWNER expects to complete Owner Review of Issue and Close Financing 2Q02 (Jun). Upon Approvals, OWNER release RFP's 3Q02 (Sep). Selected E+P+C Firm releases Long-Lead RFQ's and Subcontractor Bid Documents released 4Q02 (Dec). Construction Kick-Off scheduled 1Q03 (Jan). Project Completion 2004.
Engineering
Civil Electrical Environmental HVAC Instrumentation Mechanical Structural Process
Contracting
Civil Electrical Environmental HVAC Instrumentation Mechanical Structural General [G/C]
Project
Key Needs
Civil/Site Structural Architectural Control Room Process Equip Heat Transfer
Instrumentation Electrical Mechanical HVAC Storage Equip NDE
Piping/Fittings Insulation/Coatings Environmental Utilities Valves Pumps
Communications   Batch Process   Packaging Transportation
Energy
Energy [IEP] Boiler Turbine Generator    