Project |
| Industry Code |
| TIV |
| Project SIC Prod |
| Plant SIC |
| Environmental |
|
| LAWTON PHASE I BIG RIM TIRE MFG PLANT EXPANSION |
 |
| 12 Industrial Process Plants |
Project ID |
08000849 |
| $125,000,000 |
Verification ID |
OK020405-01 |
| 3011 Tires & Inner Tubes |
| 3011 Tires & Inner Tubes |
|
Air (A)
|
Research Date |
25/Mar/2002 |
|
| OWNER |
| Address |
| City/State |
| Phone |
| Contact |
| Title |
| E-Mail |
| DEVELOPER |
| Address |
| City/State |
| Phone |
| Contact |
| Title |
| E-Mail |
| PEC® Timing |
|
| Goodyear Tire & Rubber Company |
| 1144 East Market Street |
| Akron, OH 44316-0002 |
| (216) 796-2121 |
| Tom Frey |
| Director of Global Plants & Enginee |
| tom.frey@goodyear.com |
| Goodyear Tire & Rubber Company |
| 1 Southwest Goodyear Boulevard |
| Lawton, OK 73505-9799 |
| (580) 531-5700 |
| Jack Simpson |
| Project Director |
| jack.simpson@goodyear.com |
| E1 |
|
| Plant |
| Plant ID |
| Unit Name |
| Zone |
| Location |
| City/State |
| Phone |
| SITE.REP |
| Address |
| City/State |
| Phone |
| Contact |
| Title |
| E-Mail |
| PEC® Activity |
|
| Lawton Tire Manufacturing |
| 1009110 |
Activity |
10 Reports |
| |
| OK*01 |
County |
Comanche |
| 1 Southwest Goodyear Boulevard |
| Lawton, OK 73505-9799 |
| (580) 531-5700 |
| Goodyear Tire & Rubber Company |
| 1 Southwest Goodyear Boulevard |
| Lawton, OK 73505-9799 |
| (580) 531-5700 |
| Jack Fain |
| Project Manager |
| jack.fain@goodyear.com |
| Capital Approval (20) |
|
|
|
| OWNER has received Capital Approval for Phase I Big Rim Tire Mfg Plant Expansion. DETAILS: At existing 63,000 Tire/day plant, Upgrade/Install Tire Building Machines & Finishing Equipment plus construct 475,000 sqft Warehouse Building to meet demand for Big Rim Tires. REQUIRES: Foundations, Bldg, Tire Building Machines, Tire Finishing Equipment, Material Handling Equipment, Automated Retrieval System, Conveyors, Motors, MCC. ENVIRONMENTAL: (A) Vent/Exhaust System, Ducting. |
|
|
|
| OWNER selects Design-Build 2Q02 (Apr) to complete Preliminary Design plus release Equipment RFQ's plus Subcontractor Bid Documents 3Q02 (Jul)-4Q02. Construction Kick-Off 4Q02 (Oct). Phase I Big Rim Tire Manufacturing Plant Expansion Project Completion 2Q03. |
|
|
|
|