Project |
ALEXANDRIA POLYSTYRENE UNIT ADDITION |
|
|
| Industry Code |
07
Chemical Processing (CPI) |
Project ID |
83600162 |
| TIV |
$150,000,000 |
| Project SIC Code |
2821 Plastics Materials, Elastomers & Resins |
| Plant SIC Code |
2869 Industrial Organic Chemical |
| SIC Product |
2821*0056 Polystyrene resins-mfg |
| Environmental |
Air (A) Land (L)
|
Initial Release |
2006-09-07
|
| OWNER |
Egyptian Petrochemical Holding Company |
Plant |
Alexandria Petrochemical Complex |
| Address |
3 El Mokhayam El Dayem Street |
Plant ID |
1060352 |
Union Status |
N/A |
| City/State |
Cairo, Al Qahirah 00000 Egypt |
Unit Name |
|
| Phone |
20 2 22631000 |
Zone |
EG*02 |
County |
Al Iskandariyah |
| Contact |
Osama Kamal |
Location |
Alexandria Industrial Zone |
| Title |
Planning & Project Director |
City/State |
Alexandria, Al Iskandariyah 00000 Egypt |
| E-Mail |
ok@echem-eg.com
|
Phone |
20 2 22631000 |
| EC |
Tecnimont SpA |
SITE.REP |
Egyptian Petrochemical Holding Company |
| Address |
Viale Monte Grappa 3 |
Address |
3 El Mokhayam El Dayem Street |
| City/State |
Milano, Lombardia 20124 Italy |
City/State |
Cairo, Al Qahirah 00000 Egypt |
| Phone |
39 02 63131 |
Phone |
20 2 22631000 |
| Contact |
Gianfranco Barbieri |
Contact |
Amr Ali Fahmi |
| Title |
Project Manager |
Title |
Project Director |
| E-Mail |
g.barbieri@tecnimont.it
|
E-Mail |
|
| PEC® Timing |
C1 |
PEC® Activity |
Construction - Merit Shop |
| Scope |
OWNER awards E&C (E+P+C/M) to perform Preliminary Engineering for a Polystyrene Unit Addition. DETAILS: Construct new unit and install process (INEOS' technology) plus supporting equipment to produce 200,000 Metric T/yr High-Impact Polystyrene. REQUIRES: Reactor Vessels, Heat Exchangers, Columns, Towers, Separators, Condensers, Compressors (Gas & Air), Pumps, Motors, Piping (SS & Carbon), Pipe Racks, Temperature Sensors, Flowmeters, Control Valves, Tanks. ENVIRONMENTAL: (A) Scrubbers; (L) Liners. |
| Schedule |
OWNER and E&C continue with Preliminary Engineering through 3Q08 (Aug). Upon completion of Detailed Engineering, E&C will release RFQ's and OWNER will release Subcontractor Bid Documents 4Q08 (Dec)-1Q09. Proposed Construction Kick-Off 1Q09 (Mar). Estimated Project Completion 2Q10 (Jun). |