Brazil's Angra III Nuclear Plant Awaiting Federal Government's Authorization to Relaunch
Civil construction on the Angra III nuclear power facility began in 1985 but was suspended in 1986 because of lack of funds and the lack of a clear policy on nuclear energy.
Released Friday, April 04, 2008
Researched by Industrial Info Resources (Sugar Land, Texas)--Brazil's federal government recently announced the relaunch of the 1,350-megawatt (MW) Angra III nuclear plant, although construction won't begin until Eletrobras Termonuclear S.A. (Eletronuclear) (Rio de Janeiro, Brazil) receives authorization, which is about 30% complete. The company was expected to attend a hearing at the end of March in Angra dos Reis, Parati and Ubatuba to obtain legal permission to finish work on the building.
Civil construction on the Angra III nuclear power facility began in 1985 but was suspended in 1986 because of lack of funds and the lack of a clear policy on nuclear energy. The major part of the equipment is already on-site, and 30% of the infrastructure has been built. Eletronuclear has spent about $750 million on the plant so far, and an additional $1.84 billion will be needed to complete the facility.
The nuclear complex Central Nuclear Almirante Alvaro Alberto (Angra dos Reis, Rio de Janeiro, Brazil) is formed by Angra I, Angra II and Angra III and is strategically located near the three principal state cities of Sao Paulo, Rio de Janeiro and Belo Horizonte. Angra I and Angra II are producing 657 MW and 1,350 MW, respectively. Angra I went offline in February 2008 for maintenance and because of problems with its steam supply system. View related February 19, 2008, article - Brazil's Angra I Nuclear Plant Shuts Down for Refueling, Maintenance.
View Plant Profile - 1036032
View Project Report - 67000072
Industrial Info Resources (IIR) is a marketing information service specializing in industrial process, energy and financial related markets with products and services ranging from industry news, analytics, forecasting, plant and project databases, as well as multimedia services.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our Solutions
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Discover Our DatabaseIndustry Intel
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026
-
The Role of Contract Manufacturing in Global Pharma GrowthPodcast Episode / May 8, 2026
-
2026 North American Labor OutlookPodcast Episode / Apr 24, 2026
-
2026 European Metals & Minerals Project Spending OutlookPodcast Episode / Apr 7, 2026