Researched by Industrial Info Resources (Sugar Land, Texas)--July 8 marked the beginning of a new set of revised safety standards for nuclear reactors in Japan. Following the restructuring of the Nuclear and Industrial Safety Agency into a new branch of the Ministry of the Environment, the Nuclear Regulation Authority (NRA), Japanese power companies were left in an awkward position--they had to improve safety at their nuclear power plants, but had no firm set of standards to guide their efforts. Most companies simply went forward and performed what work was believed to be necessary, in hopes that it would meet the new standards. Four of those companies already have applied to restart 10 reactors at five power stations in Japan.
The four companies that applied for restart on July 8 are Hokkaido Electric Power Company Incorporated (TYO:9509) (Hokuden) (Sapporo, Japan), Kansai Electric Power Company Incorporated (TYO:9503) (Kanden) (Osaka, Japan), Shikoku Electric Power Company Incorporated (TYO:9507) (Yonden) (Takamatsu, Japan), and Kyushu Electric Power Company Incorporated (TYO:9508) (Kyuden) (Fukuoka, Japan).
Hokuden is applying to restart all three units at its Tomari Nuclear Power Station in southern Hokkaido, the most units at any one station. Kanden is applying to restart four units in two nuclear power stations: units 3 and 4 at Oi, and units 3 and 4 at Takahama. Both of Kanden's stations are in the Fukui prefecture. The other three units in the application process for restarts are units 1 and 2 at Kyuden's Sendai station in the Kagoshima prefecture, and Unit 3 at Yonden's Ikata station in the Ehime prefecture.
While Tokyo Electric Power Company Incorporated (TYO:9501) (Tokyo) (TEPCO) has announced its intention to apply to restart units 6 and 7 at its Kashiwazaki-Kariwa power station in the Niigata prefecture, the remaining four companies have made no announcements about restarting their reactors.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
The four companies that applied for restart on July 8 are Hokkaido Electric Power Company Incorporated (TYO:9509) (Hokuden) (Sapporo, Japan), Kansai Electric Power Company Incorporated (TYO:9503) (Kanden) (Osaka, Japan), Shikoku Electric Power Company Incorporated (TYO:9507) (Yonden) (Takamatsu, Japan), and Kyushu Electric Power Company Incorporated (TYO:9508) (Kyuden) (Fukuoka, Japan).
Hokuden is applying to restart all three units at its Tomari Nuclear Power Station in southern Hokkaido, the most units at any one station. Kanden is applying to restart four units in two nuclear power stations: units 3 and 4 at Oi, and units 3 and 4 at Takahama. Both of Kanden's stations are in the Fukui prefecture. The other three units in the application process for restarts are units 1 and 2 at Kyuden's Sendai station in the Kagoshima prefecture, and Unit 3 at Yonden's Ikata station in the Ehime prefecture.
While Tokyo Electric Power Company Incorporated (TYO:9501) (Tokyo) (TEPCO) has announced its intention to apply to restart units 6 and 7 at its Kashiwazaki-Kariwa power station in the Niigata prefecture, the remaining four companies have made no announcements about restarting their reactors.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/iirenergy/industry-news/article.jsp
Want More IIR News?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On Google
Loading...
Refer This Article
Ask Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Explore Our EnergyLive Tools
EnergyLive Tools provide instant insight into new build, outages, maintenance, and capacity shifts across key energy sectors.
Learn MoreRelated Articles
-
Japan Closer to Restarting World's Largest Nuclear Power Pla...December 05, 2025
-
Japan's Kyushu Electric Prepares for Restart of Second Nucle...September 29, 2015
-
Kyushu Electric Suspends Power Build-up at Restarted Sendai ...August 24, 2015
-
Japan's Nuclear Regulators Give All Clear to Two Reactors at...September 22, 2014
Explore Our Enery Industry Reports
Gain the competitive edge with IIR Energy’s suite of energy market reports, designed for traders, analysts, and asset managers who rely on verified, real-time data.
Learn MoreIndustry Intel
-
From Data to Decisions: How IIR Energy Helps Navigate Market VolatilityOn-Demand Podcast / Nov. 18, 2025
-
Navigating the Hydrogen Horizon: Trends in Blue and Green EnergyOn-Demand Podcast / Nov. 3, 2025
-
ESG Trends & Challenges in Latin AmericaOn-Demand Podcast / Nov. 3, 2025
-
2025 European Transportation & Biofuels Spending OutlookOn-Demand Podcast / Oct. 27, 2025
-
2025 Global Oil & Gas Project Spending OutlookOn-Demand Podcast / Oct. 24, 2025