Permitting Process Pushes Back Boardman-Hemingway Transmission Line Construction by Two Years Hero Image

Power

Permitting Process Pushes Back Boardman-Hemingway Transmission Line Construction by Two Years

Construction of the 500-kilovolt (kV) Boardman-Hemingway Transmission Line from Oregon to Idaho has been pushed back at least two years, due to permitting and regulatory issues.

Released on Tuesday, January 07, 2014
Researched by Industrial Info Resources (Sugar Land, Texas)--Construction of the 500-kilovolt (kV) Boardman-Hemingway Transmission Line from Oregon to Idaho has been pushed back at least two years, due to permitting and regulatory issues. The 300-mile, overhead, single-circuit transmission line is part of the Energy Gateway Project.

The line will be constructed from a proposed 500-kV Idaho Power (Boise, Idaho) substation in Boardman, Oregon, to Idaho Power's existing Hemingway Substation in Melba, Idaho.

Originally, construction of the line was scheduled to begin in 2015. Permitting and regulatory issues have pushed the start time out to 2017, or even 2018.

The permitting process can take years when a line crosses state boundaries and involves multiple developers. The permitting process includes consideration of economic factors and environmental and social issues.

However, the U.S. Department of Energy is fast-tracking the Boardman-Hemingway Line project. Tetra Tech Incorporated (NASDAQ:TTEK) (Boise) is serving as environmental consultant for the project.

In 2012, PacifiCorp (Portland, Oregon) and Bonneville Power Administration (Portland) joined the project. PacifiCorp will pay 54.55% of the permitting cost, Bonneville Power Administration will pay 24.24%, and Idaho Power will pay 21.21%.

View Project Report - 22001416

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/iirenergy/industry-news/article.jsp
Share This Article

Want More IIR News?

Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 37 + 4?
Loading...

Refer This Article


Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

Explore Our EnergyLive Tools

EnergyLive Tools provide instant insight into new build, outages, maintenance, and capacity shifts across key energy sectors.

Learn More
Explore Our Enery Industry Reports

Gain the competitive edge with IIR Energy’s suite of energy market reports, designed for traders, analysts, and asset managers who rely on verified, real-time data.

Learn More
Industry Intel


Explore Our Coverage

Industries


  • Power Generation
  • Petroleum Refining
  • Natural Gas
  • Natural Gas Liquids
  • Petrochemicals
  • Renewable Fuels

Trending Sectors


  • Data Centers
  • LNG