Researched by Industrial Info Resources (Sugar Land, Texas)--Samsung's first fabrication facility at its semiconductor campus in Taylor, Texas, likely will not be operational until 2026. The company previously had announced a July 2024 startup date.
According to local media, Samsung will delay ordering the $10 billion project's production machinery until a decision is made on what type of chips its facility will produce. Subscribers to Industrial Info's Global Market Intelligence (GMI) Industrial Manufacturing Plant and Project databases can learn more from a detailed plant profile and project report.
Samsung could change the plant's product from the proposed 4-nanometer (nm) chip to the newer 2-nm variety, which would speed up data processing and reduce power consumption. This would make it a better fit for artificial intelligence (AI) technology.
Samsung says it will make a final decision on the product before the end of the third quarter. How this would affect the construction schedule for the remaining nine phases of the Taylor campus is yet to be seen. Subscribers can click here for a list of detailed project reports related to the Taylor campus.
Industrial Info Resources (IIR) is the leading provider of industrial market intelligence. Since 1983, IIR has provided comprehensive research, news and analysis on the industrial process, manufacturing and energy related industries. IIR's Global Market Intelligence (GMI) platform helps companies identify and pursue trends across multiple markets with access to real, qualified and validated plant and project opportunities. Across the world, IIR is tracking more than 200,000 current and future projects worth $17.8 trillion (USD).
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Explore Our EnergyLive Tools
EnergyLive Tools provide instant insight into new build, outages, maintenance, and capacity shifts across key energy sectors.
Explore Our ToolsRelated Articles
-
U.S. Tech Titans Eye Semiconductor, Computer Project StartsSeptember 21, 2026
-
ISM: Tariffs Continue to Drive Contraction in U.S. Manufactu...October 03, 2025
Explore Our Enery Industry Reports
Gain the competitive edge with IIR Energy’s suite of energy market reports, designed for traders, analysts, and asset managers who rely on verified, real-time data.
View ReportsIndustry Intel
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1, CDMO and ReshoringPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026