As Permian Gets Gassier, Takewaway Capacity Ramps Up to Maintain Crude Production

A significant number of new pipelines are in various stages of planning and development in the Permian Basin

Released Thursday, June 06, 2024

As Permian Gets Gassier, Takewaway Capacity Ramps Up to Maintain Crude Production

Written by Paul Wiseman for Industrial Info Resources (Sugar Land, Texas)--A significant number of new pipelines are in various stages of planning and development in the Permian Basin. The goal is more about maintaining oil production than handling gas, according to Shane Mullins, Industrial Info's vice president of energy products and project development, but unless the associated gas has a pathway out, oil production could be inhibited.

"Permian Basin oil production is still growing, just not at the pace it did in previous years," Mullins said. "Combine that with the fact that the area's gas-to-oil ratio (GOR) is increasing, and you clearly see that natural gas takeaway capacity must continue to grow, even if crude production slows down somewhat."

The Permian's oil production growth has exceeded predictions for several years, and predicted 2024 growth still ranges from 190,000 to 380,000 barrels per day (BBL/d). Mullins said that while this amount is down from the 1 million BBL/d of last year, it is still significant.

Associated gas is also expected to grow by 8 billion cubic feet per day (Bcf/d) by 2030, so the Matterhorn pipeline (see below), which is expected to start service in September 2024, is only a start toward alleviating the backlog of production that led to negative Waha Hub prices and flaring that happened earlier this year.

And according to the U. S. Energy Information Administration (EIA), "The Permian region in western Texas and New Mexico produces the second-most U.S. natural gas, accounting for 19% of production in the United States."

The good news is that "We could see another major pipeline of 2 Bcf/d of takeaway capacity reach FID (final investment decision) before year's end and another in the next year," said Mullins (see list below).

Another issue straining takeaway capacity is the increase in regulations on flaring and methane leaks, removing options that used to provide a safety valve for pipeline constraints.

Mullins noted that, while the majority of Permian gas goes to the Gulf Coast, mainly in Texas, there's so much gas now, there's plenty to also go by pipeline across the Texas border into Mexico, as well as further west to Mexican liquefied natural gas (LNG) plants under construction.

Here are the main natural gas pipeline projects Industrial Info is tracking, by year expected in service. Some involve turning new dirt, while others will be about boosting capacity of existing lines:
  • Matterhorn Express. Designed to transport up to 2.5 Bcf/d from the Permian Basin to Katy, west of Houston, Industrial Info expects it to go into service in September 2024. Subscribers to Industrial Info's Global Market Intelligence (GMI) Oil & Gas Pipelines Project Database can click here for the related project reports.
Proposed Lines
There are five in this category being tracked by Industrial Info:
  • Gulf Coast Express Expansion. Gulf Coast Express Pipeline, LLC, is a joint venture (JV) between Kinder Morgan Incorporated (NYSE:KMI) (Houston, Texas), DCP Midstream (part of Phillips 66 (NYSE:PSX) [Houston]), ArcLight Capital Partners (Boston, Massachusetts), and Kinetik Holdings (Midland, Texas). The expansion is expected to add 570 million cubic feet per day of natural gas capacity to the 500-mile line's existing 2 Bcf/d. This line carries Permian gas to Agua Dulce. Subscribers can click here for the project reports.
  • Apex. Targa Resources Corporation (NYSE:TRGP) (Houston) received Texas Railroad Commission approval in 2023 to build this 42" pipeline 563 miles from the Permian to Houston and Southwest Louisiana. With a capacity of 2 Bcf/d and a projected cost of $2 billion-2.5 billion, the company expects an FID by the end of 2024. Subscribers can click here for the project reports.
  • Warrior. Energy Transfer LP (NYSE:ET) (Dallas, Texas) is developing a 325-mile line from the Permian to its Ellis County interconnect with lines that continue to the Gulf Coast. The company has reported that the line could be completed within two years of FID. Subscribers can click here for the project reports.
  • DeLa Express, LLC. In April, this affiliate of Moss Lake Partners (Houston) announced it was seeking approval from the Federal Energy Regulatory Commission (FERC) to start pre-filing for a pipeline intended to originate in the Delaware Basin and deliver that gas to markets in the Lake Charles, Louisiana, area. The 690-mile, 42-inch line is expected to transport 2 Bcf/d of natural gas liquids-rich natural gas. If approved, the project would also include five lateral lines, eight compressor stations, many meter stations, and other facilities. The opening date would be in 2028. Subscribers can click here for the project reports.
  • ADCC Pipeline. Although it does not directly come from the Permian, some of the gas at this line's origination point, Agua Dulce, originates there. ADCC is a joint venture between Whistler Pipeline, LLC and Cheniere Energy Incorporated (NYSE:LNG) (Houston). ADCC is designed to carry 1.7 Bcf/d from the terminus of the Whistler pipeline in Agua Dulce, Texas, to Cheniere's Corpus Christi LNG plant. Expandable to 2.5 Bcf/d, Industrial Info expects it to be in service in the third quarter. Subscribers can click here for the project report. Additionally, in a transaction expected to close in this quarter, ADCC will be part of a joint venture among Enbridge Incorporated (NYSE:ENB) (Calgary, Alberta), WhiteWater/I Squared (Miami, Florida) and MPLX LP (Findlay, Ohio). The plan is to connect ADCC with the existing Rio Bravo pipeline. One of the goals will be to connect Permian gas with NextDecade's (NASDAQ:NEXT) (Houston) Rio Grande LNG plant, where the first three LNG trains are currently under construction.
Down (and Across) Mexico Way
Those are the lines heading to the Gulf Coast, Texas and Louisiana. Cross-border exports are also in the works, Mullins said. "Although many are thinking about building a new pipeline from the Permian to the Mexico border, we already have 20 Bcf/d in existing pipeline capacity heading in that direction that's underutilized. We're already pushing a record amount of gas to Mexico through the NET Mexico Pipeline and the Sur de Texas (Tuxpan) line heading to Monterrey. (Industrial Info) monitors flow rates at dozens of connections on those lines every hour of every day."

Exports to Mexico have risen substantially year-over-year, "and there's more room to grow," Mullins said.

Other pipelines to Mexico are heading way out west, to LNG plants in Baja California. In February, FERC approved the Saguaro pipeline, which would carry about 2.8 Bcf/d from the Permian to Mexico Pacific's proposed Saguaro LNG export plant on the west coast of Mexico. Mullins noted that, if the Biden administration's pause on approvals is released post-election, construction could begin in 2025. Subscribers can click here for projects relating to the Saguaro LNG plant and pipeline.

Even without the new line, the plant could be fed by existing lines, according to Industrial Info data. "Our projections see US-to-Mexico exports growing by 0.5 Bcf/d by 2025 and by 2-3 Bcf/d by 2030--without building a new pipeline," Mullins said.

Industrial Info Resources (IIR) is the leading provider of industrial market intelligence. Since 1983, IIR has provided comprehensive research, news and analysis on the industrial process, manufacturing and energy related industries. IIR's Global Market Intelligence (GMI) platform helps companies identify and pursue trends across multiple markets with access to real, qualified and validated plant and project opportunities. Across the world, IIR is tracking more than 200,000 current and future projects worth $17.8 trillion (USD).
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 14 + 2?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

PECWeb Global Market Intelligence Platform

Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.

Discover Pecweb

Get notifications from IIR News Intelligence

Click 'Sign Up' then 'Allow'