Eskom's 4,800-Megawatt Project Begins Power Production after Major Schedule Creep power station began producing electricity last week in South Africa, about seven and a half years after construction began. The coal-fired facility, owned by Eskom (Johannesburg, South Africa), is expected to ramp up to full power in three months. Within this article: Details of the Medupi power plant project by Eskom."> power station began producing electricity last week in South Africa, about seven and a half years after construction began. The coal-fired facility, owned by Eskom (Johannesburg, South Africa), is expected to ramp up to full power in three months. Within this article: Details of the Medupi power plant project by Eskom."> power station began producing electricity last week in South Africa, about seven and a half years after construction began. The coal-fired facility, owned by Eskom (Johannesburg, South Africa), is expected to ramp up to full power in three months. Within this article: Details of the Medupi power plant project by Eskom.">
Join us on January 28th for our 2026 North American Industrial Market Outlook. Register Now!
Sales & Support: +1 800 762 3361
Member Resources
Industrial Info Resources Logo
Global Market Intelligence Constantly Updated Your Trusted Data Source for Industrial & Energy Market Intelligence
Home Page
Released on Wednesday, March 11, 2015

Power

Eskom's 4,800-Megawatt Project Begins Power Production after Major Schedule Creep

The Medupi power station in South Africa has begun to produce electricity

Written by Richard Finlayson, Senior International Editor for Industrial Info Resources (Sugar Land, Texas)--The long-awaited, 4,800-megawatt Medupi power station began producing electricity last week in South Africa, about seven and a half years after construction began. The coal-fired facility, owned by Eskom (Johannesburg, South Africa), is expected to ramp up to full power in three months.

Construction on the project began in August 2007. At that time, the last of six planned units was scheduled to go on-grid in 2015. The project had a planned investment of SA rand (SAR) 80 billion (about $7 billion at current exchange rates).

The estimated total investment is now SAR 120 billion (about $10.5 billion), and the date for full power by all six units is now set for sometime in 2019. The second unit is scheduled for synchronization with the grid in 2016-17.

State-owned Eskom also hopes to commission the first unit for Medupi's "twin" 4,800-MW project, Kusile, sometime in 2016.

There was some self-congratulation by government and Eskom officials, including new Chief Executive Officer Tshediso Matona, who said, "The electricity flowing into the grid marks a new beginning." With load shedding and power supply quotas affecting the country's domestic and industrial users, the most generous reaction to the official excitement is, "About time too."

For related information, see December 2, 2014, article - South Africa's Eskom Battles Murphy's Law at Mega Projects.

The grid is now receiving an additional 1,500 MW from a renewable projects pipeline, but still needs at least one of the major projects to be brought online to add to the installed capacity of 42,000 MW, which would allow a reasonable reserve margin on the system. Many of the units in the ageing, mainly coal-fired national fleet need to be taken off-grid for unscheduled maintenance. This could reduce available power capacity by as much 25% at various times.

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and 10 international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp false
Share This Article
Want More IIR News?

Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 72 + 8?
Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Learn More
Industrial Project Opportunity Database and Project Leads

Get access to verified capital and maintenance project leads to power your growth.

Learn More
Industry Intel


Explore Our Coverage

Industries


  • Electric Power
  • Terminals
  • Pipelines
  • Production
  • Alternative Fuels
  • Petroleum Refining
  • Chemical Processing
  • Metals & Minerals
  • Pulp, Paper & Wood
  • Food & Beverage
  • Industrial Manufacturing
  • Pharmaceutical & Biotech

Trending Sectors


  • Data Centers
  • Semiconductors
  • Battery Supply Chain
  • Packaging
  • Nuclear Power
  • LNG
IIR Logo Globe

Site-wide Scheduled Maintenance for September 27, 2025 from 12 P.M. to 6 P.M. CDT. Expect intermittent web site availability during this time period.

×
×

Contact Us

For More Info!