Loading…

Power

First 600-Megawatt Unit of China Power Investment's Yanshanhu Power Plant Begins Trial Operation in Liaoning

The startup test for the first 600-megawatt unit of China Power Investment Corporation's Yanshanhu Power Plant was completed and began trial operation on October 16, 2011.

Released Thursday, October 27, 2011

First 600-Megawatt Unit of China Power Investment's Yanshanhu Power Plant Begins Trial Operation in Liaoning

Researched by Industrial Info Resources (Sugar Land, Texas)--The startup test for the first 600-megawatt (MW) unit of China Power Investment Corporation's (CPIC) (Beijing) Yanshanhu Power Plant was completed and began trial operation on October 16, 2011. The first startup, the first connection to the grid and first load test were all completed during the startup test, and various parameters are satisfactory with the design specifications, the State Grid Corporation of China (Beijing) announced on October 20.

Yanshanhu Power Plant is at Goumenzi Village in Longcheng District, in northeast China's Liaoning province. CPIC plans to build two 600-MW and four 1,000-MW coal-fired units by using the rich coal resources in its Baiyinhua Coal Mine. Two 600-MW, supercritical, air-cooling, coal-fired units will be built in Phase I, with a total investment of about $740 million. According to the schedule, the power plant will be connected to the State Grid via the 500-kilovolt (KV) Chaoyang substation in the northern part of the site.

The Phase I project received approval from the National Development and Reform Commission on June 24, 2009. Grounding breaking ceremony then kicked off on August 20, 2009.

Presently, the Northeast Electric Power Research Institute (Shenyang, Liaoning), a subsidiary of the State Grid Liaoning Electric Power Company Limited (Shenyang, Liaoning), is responsible for various load tests for Unit 1. The combined test of the 500-kV transmission line for Unit 2 have been completed, and the transmission line is ready to be energized. The overall startup scheme of Unit 2 has been submitted to the dispatching center. In the next stage, the load tests for both units will be performed at the same time.

Following the completion of Phase I, construction of Phase II will begin shortly. When the power plant is fully completed, it will be the largest coal-fired power plant in northeast China.

View Project Report - 88001153

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 49 + 9?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

PECWeb Global Market Intelligence Platform

Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.

Discover Pecweb

Get notifications from IIR News Intelligence

Click 'Sign Up' then 'Allow'