Gupta Energy Completes 120-Megawatt Chandrapur Project
After a delay of more than 18 months, Gupta Energy Private Limited has completed its 120-megawatt Chandrapur project, which comprises of two 60-MW units, both of which are operational.
Released Thursday, September 27, 2012
Reports related to this article:
Researched by Industrial Info Resources India (Delhi, India)--After a delay of more than 18 months, Gupta Energy Private Limited (Nagpur, Maharashtra) has completed its 120-megawatt (MW) Chandrapur project, which comprises of two 60-MW units, both of which are now operational.
The project, which was due to be commissioned by March 2012, has been delayed partly bacause of bad weather conditions and a snag in the turbo generator system. According to Gupta Energy sources, the second unit of the project was synchronized on May 10, 2012, while the commissioning of the first unit was achieved on September 17, 2012 because of a mechanical glitch in the rotor.
Gupta Energy Private Limited is a special purpose vehicle of coal-beneficiation and washery major Gupta Coal India Limited (Nagpur, India). Developed at Usegaon in the Chandrapur district of the state, the washery reject-based power plant is India's first commercial-scale power unit of its kind.
The power plant has two Circulating Fluidized Bed-combustion boilers of 250-tonne-per-hour capacity, which are supplied by Chinese equipment manufacturer, Ningguo Thaichen Elec-industrial Company Limited (Ningguo, China). The boilers would be fed with an 80:20 blend of washery reject and F-grade of indigenous raw coal.
About 3,000 tonnes of coal reject would be required per day to run the plant at full capacity. The coal reject will be sourced from the washeries of Gupta Coal, which are located in the Vidarbha region of Maharashtra. The water requirement for the power plant has been estimated at 11,400 cubic meters per day, which will be sourced from the adjacent Warda River.
The company already has entered into a power purchase agreement with Tata Power Trading Company. The tariff for the supply of power would range between 2.60 to 3.55 Indian rupees per unit, depending on the demand.
As a part of forward integration of its coal business, Gupta Group has ventured into power generation. It is in the process of establishing independent power plants utilizing both conventional and non-conventional energy sources.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
U.S. Boosts T&D Overhauls with SPARK InvestmentsSeptember 28, 2026
-
FERC-NERC: Winter Grid Gains, but Persistent Risks RemainSeptember 28, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026
-
2026 Global Power Demand Outlook: Gas, Nuclear & RenewablesPodcast Episode / Sep 18, 2026
-
2026 Oil & Gas CapEx Outlook: Middle East, LNG & PermianPodcast Episode / Sep 4, 2026
-
The Answer Age Starts with Trusted Data: Introducing IIR Envoy™ MCPPodcast Episode / Sep 1, 2026
-
European Chemicals and Transport Fuels OutlookPodcast Episode / Jul 10, 2026