Investment for Western Ireland Grid Development Totals 240 Million
State-owned grid operator EirGrid has appointed Tobin Consulting Engineers to lead a consortium to work on the first phase of a 240 million ($306 million) grid development ...
Released Monday, January 09, 2012
Researched by Industrial Info Resources Europe (Galway, Ireland)--Irish state-owned grid operator EirGrid (Dublin) has appointed Tobin Consulting Engineers (Galway, Ireland) to lead a consortium to work on the first phase of a 240 million ($306 million) grid development project in Mayo County, which is in western Ireland.
The project, which is known as the Grid West Project, is part of the larger 3.2 billion ($4 billion) Grid25 redevelopment strategy for the Irish grid. The strategy is due to be implemented between now and 2025, and work will involve strengthening the existing infrastructure in Mayo and surrounding counties. One of the major goals of the exercise is to underpin the region's ability to attract investment, which could lead to expansion across a variety of manufacturing industries, as well as more opportunities to develop renewable energy.
The Irish Wind Energy Association (Naas, County Kildare) estimates that Ireland has a wind generation potential of 6,000 megawatts (MW) onshore and 4,000 MW offshore, particularly in the western areas; however, the current grid infrastructure is not sufficiently developed to handle further energy. For additional information, see November 25, 2011, article - Ireland Ready to Upgrade Electricity Grid.
Two other projects that could benefit from the Grid West development are Crystal Energy's 200-MW, natural gas-fired power plant and Lupset Investment's 200-MW, natural gas-fired peaking power plant, both of which are planned for Bellacorick, in northern Mayo.
In related news, work to repair an electricity interconnector between Northern Ireland and Scotland has fallen behind schedule and could cost up to 24.37 million ($31 million). Both submarine cables, which run between Islandmagee and Ayrshire in Scotland, have been out of action since July and August 2011, respectively. The fault in one of the underwater cables has been detected. When it is fixed, work on the other will begin. However, sea currents and weather conditions have hampered progress in the repairs, which are now behind schedule. Economist John Simpson warned: "If a power station now tripped, there's a risk that we would have the lights going out, if it was at a peak period during the day or during the evening."
View Project Report - 300051154 30051682
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our Solutions
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Brazil Critical Minerals 2027: Rare Earths, Lithium, CopperPodcast Episode / Oct 16, 2026
-
US Craft Labor Outlook 2026: Wages, Per Diems, Data CentersPodcast Episode / Oct 16, 2026
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026