Phase-II Construction of China's Puqi Power Plant Kicks Off in Hubei
Following the pouring of concrete for the main powerhouse on October 28, 2010, Phase-II construction of the Puqi Power Plant kicked off in Central China's Hubei province.
Released Monday, November 08, 2010
Researched by Industrial Info Resources (Sugar Land, Texas)--Following the pouring of concrete for the main powerhouse on October 28, 2010, Phase-II construction of the Puqi Power Plant kicked off in Central China's Hubei province.
The Phase II expansion project entails the construction of two 1000-megawatt (MW) Chinese-made, ultra-supercritical coal-fired units. Total investment in the project will be about $1.03 billion. The project will be adopted with secondary recycled water for cooling, and the annual water consumption will be about 24.6 million cubic meters. The project will also be furnished with high-efficiency electrostatic dust removal systems, desulfurization and denitration devices, and online continuous monitoring devices.
The Puqi Power Plant is the first foreign-invested power plant in Hubei. The power plant currently has two 300-MW units, which were commissioned in June and October 2004. In June 2006, China Resources Power signed the agreement with the government of the Hubei province to construct two 1,000-MW coal-fired units at the existing plant. In December 2004, the owner submitted the project proposal to the National Development and Reform Commission (NDRC). Construction preparation began in August 2009.
On April 14, 2010, the expansion project received approval from the NDRC. On May 26, 2010, China Resources Power Hubei Company Limited (Chibi, Hubei), a regional subsidiary of China Resources Power Holdings Limited (HKG:0836) (Hong Kong), officially awarded the engineering and survey contract to Central Southern China Electric Power Design Institute (Wuhan, Hubei), a regional subsidiary of China Power Engineering Consultancy Corporation (Beijing).
According to the schedule, the project will begin operations by the end of 2012. Upon completion, the project will consume about 3.9 million metric tons of coal per year and produce about 12 billion kilowatt-hours of electricity annually.
View Project Report - 88000797
Industrial Info Resources (IIR) is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. IIR's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Europe's Mild Winter Outlook Tests Natural Gas PreparednessOctober 16, 2026
-
South Korea's US$747 Billion Energy Transition PlanOctober 16, 2026
-
Trump Admin Continues Offshore Wind War with Revolution Wind...October 15, 2026
-
U.S. Nuclear Body Gives Second SMR Permit in Six MonthsOctober 15, 2026
-
Europe Makes its First SMR InvestmentOctober 14, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1, CDMO and ReshoringPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026