Released July 18, 2022 | SUGAR LAND
en
North America
Suncor Canada, on July 15, started a 73-day planned maintenance turnaround of the 90,000-barrel-per-day (BBL/d) Fluid Coker 8-1 unit at its 265,000-BBL/d Mildred Lake Oil Sands Upgrader and Refinery in Fort McMurray, Alberta.
International
KirishiNefteOrgSyntez is performing planned maintenance on the 39,600-BBL/d Visbreaker unit at its 420,000-BBL/d Kirishi Refinery in Russia. The unit restart is expected at the end of July.
LUKOIL-Permnefteorgsintez is performing planned maintenance on the 7,080-BBL/d Reformer L-35-8/300B (Aromatics) unit at its 273,800-BBL/d Perm Refinery in Russia. The unit restart is expected by mid-August.
Astron Energy tentatively plans to restart its 100,000-BBL/d Cape Town Refinery in South Africa, beginning September 15. The refinery has been under an unplanned shutdown since July 2, 2020, due to a unit fire. The shutdown includes 11 major units.
Industrial Info Resources (IIR) is the world's leading provider of market intelligence across the upstream, midstream and downstream energy markets and all other major industrial markets. IIR's Global Market Intelligence Platform (GMI) supports our end-users across their core businesses, and helps them connect trends across multiple markets with access to real, qualified and validated project opportunities. Follow IIR on: LinkedIn.
Suncor Canada, on July 15, started a 73-day planned maintenance turnaround of the 90,000-barrel-per-day (BBL/d) Fluid Coker 8-1 unit at its 265,000-BBL/d Mildred Lake Oil Sands Upgrader and Refinery in Fort McMurray, Alberta.
International
KirishiNefteOrgSyntez is performing planned maintenance on the 39,600-BBL/d Visbreaker unit at its 420,000-BBL/d Kirishi Refinery in Russia. The unit restart is expected at the end of July.
LUKOIL-Permnefteorgsintez is performing planned maintenance on the 7,080-BBL/d Reformer L-35-8/300B (Aromatics) unit at its 273,800-BBL/d Perm Refinery in Russia. The unit restart is expected by mid-August.
Astron Energy tentatively plans to restart its 100,000-BBL/d Cape Town Refinery in South Africa, beginning September 15. The refinery has been under an unplanned shutdown since July 2, 2020, due to a unit fire. The shutdown includes 11 major units.
Industrial Info Resources (IIR) is the world's leading provider of market intelligence across the upstream, midstream and downstream energy markets and all other major industrial markets. IIR's Global Market Intelligence Platform (GMI) supports our end-users across their core businesses, and helps them connect trends across multiple markets with access to real, qualified and validated project opportunities. Follow IIR on: LinkedIn.