Motiva, on September 26, started 40 days of planned maintenance on the 90,000-barrel-per-day (BBL/d) Vacuum Pipe Still (VPS) 2, 40,000-BBL/d Vacuum Tower 2 and MPU 3 (N-Methyl-Pyrrolidone) units at its 640,000-BBL/d refinery in Port Arthur, Texas.
ExxonMobil's Fluid Catalytic Cracker Unit (FCCU) at its 600,000-BBL/d refinery in Beaumont, Texas, experienced a process upset on Monday, and as a result, the unit will be reduced 10% until this upcoming weekend while minor repairs are underway.
International
Reliance Industries Limited, on September 26, began a 21-day planned turnaround of the 175,000-BBL/d delayed coker unit at its 780,000-BBL/d Jamnagar SEZ Refinery in India. Expectations are to restart the unit by October 16.
TotalEnergies SE's 1,060 million-pound-per-year Naphtha Cracker 3 ethylene unit at its 360,000-BBL/d refinery in Antwerpen, Belgium, remains offline after being shut down for a maintenance turnaround in late September. The unit is expected to resume operation in early December. Meanwhile, the 50,000-BBL/d FCCU 1, which was forced to shut down on August 6 following a fire, remains offline and is tentatively expected to restart by early December.
Industrial Info Resources (IIR) is the leading provider of industrial market intelligence. Since 1983, IIR has provided comprehensive research, news and analysis on the industrial process, manufacturing and energy related industries. IIR's Global Market Intelligence (GMI) helps companies identify and pursue trends across multiple markets with access to real, qualified and validated plant and project opportunities. Across the world, IIR is tracking over 200,000 current and future projects worth $17.8 Trillion (USD).
Motiva, on September 26, started 40 days of planned maintenance on the 90,000-barrel-per-day (BBL/d) Vacuum Pipe Still (VPS) 2, 40,000-BBL/d Vacuum Tower 2 and MPU 3 (N-Methyl-Pyrrolidone) units at its 640,000-BBL/d refinery in Port Arthur, Texas.
ExxonMobil's Fluid Catalytic Cracker Unit (FCCU) at its 600,000-BBL/d refinery in Beaumont, Texas, experienced a process upset on Monday, and as a result, the unit will be reduced 10% until this upcoming weekend while minor repairs are underway.
International
Reliance Industries Limited, on September 26, began a 21-day planned turnaround of the 175,000-BBL/d delayed coker unit at its 780,000-BBL/d Jamnagar SEZ Refinery in India. Expectations are to restart the unit by October 16.
TotalEnergies SE's 1,060 million-pound-per-year Naphtha Cracker 3 ethylene unit at its 360,000-BBL/d refinery in Antwerpen, Belgium, remains offline after being shut down for a maintenance turnaround in late September. The unit is expected to resume operation in early December. Meanwhile, the 50,000-BBL/d FCCU 1, which was forced to shut down on August 6 following a fire, remains offline and is tentatively expected to restart by early December.
Industrial Info Resources (IIR) is the leading provider of industrial market intelligence. Since 1983, IIR has provided comprehensive research, news and analysis on the industrial process, manufacturing and energy related industries. IIR's Global Market Intelligence (GMI) helps companies identify and pursue trends across multiple markets with access to real, qualified and validated plant and project opportunities. Across the world, IIR is tracking over 200,000 current and future projects worth $17.8 Trillion (USD).