Turbine Upgrades at Grand Coulee Dam Completed

The U.S. Bureau of Reclamation/Department of the Interior-Pacific Northwest Regional Office (Boise, Idaho) has completed turbine runner upgrades...

Released Thursday, December 30, 2010

Turbine Upgrades at Grand Coulee Dam Completed

Researched by Industrial Info Resources (Sugar Land, Texas)--The U.S. Bureau of Reclamation/Department of the Interior-Pacific Northwest Regional Office (Boise, Idaho) has completed turbine runner upgrades on units G-1 through G-18 of the Francis turbine generators in the Left and Right powerhouses of the Grand Coulee Dam. The project commenced construction in July 1999 and was completed this month.

The Left Powerhouse contains nine turbine/generators, each rated at 125 megawatts (MW). The Right Powerhouse contains nine turbine/generators, each rated at 125 MW. The cost of the project was about $100 million. Efficiency was increased more than 3.5%, more than was expected.

The Grand Coulee Dam is the largest hydroelectric generation facility in North America. The Right and Left powerhouses were constructed between 1933 and 1942 and originally generated 1,974 MW. A third powerhouse was completed in 1974, and pumped-storage plant was completed in 1973, making a total generation of 6,809 MW for all four powerhouses.

Grand Coulee impounds a reservoir, Franklin D. Roosevelt Lake, named for the president who authorized construction of the dam.

Andritz Hydro (Charlotte, North Carolina) and GE Hydro (Lachine, Quebec) performed work on the project, the scope of which consisted of the installation of new turbine runners, new wicket gates, the refurbishment of associated equipment and re-installation of the turbines.

View Plant Profile - 1024881
View Project Report - 21000475

Industrial Info Resources (IIR) is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. IIR's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 79 + 1?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

PECWeb Global Market Intelligence Platform

Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.

Discover Pecweb

Get notifications from IIR News Intelligence

Click 'Sign Up' then 'Allow'