Oleoducto Bicentenario de Colombia SAS Delays Phases 2, 3 of Pipeline Project
A lengthy environmental permitting process has forced Oleoducto Bicentenario de Colombia SAS to postpone the second and third phases of a 1,000-kilometer (621-mile) crude oil pipeline project, according to the company.
Released Monday, December 30, 2013
Reports related to this article:
Researched by Industrial Info Resources Latin America (Cordoba, Argentina)--A lengthy environmental permitting process has forced Oleoducto Bicentenario de Colombia SAS (Bogotá, Colombia) to delay the second and third phases of a 1,000-kilometer (621-mile) crude oil pipeline project, according to the company.
A spokesman for the Oleoducto Bicentenario (OBC) project said the delay has been caused by Colombian environmental policies, which require a lengthy permitting process.
Oleoducto Bicentenario de Colombia SAS, which was formed by seven firms that joined especially for the development of the pipeline project, is performing environmental-impact studies. The study reports will be given to environmental authorities during the first quarter of 2014. The permitting results will not be known until 18 months after the reports are completed.
If the permits are granted after that period, Oleoducto Bicentenario de Colombia SAS will pick an engineering, procurement and construction (EPC) firm to continue the engineering of the second and third phases of the project.
SICIM Spa (Bogotá, Colombia) won an EPC contract for the first phase of the project, which included the installation of 230 kilometers (142 miles) of the 42-inch pipeline from Araguaney to Banadia. The first phase also included construction of tanks in existing storage Terminals (Araguaney and Coveñas) and the installation of a provisional pumping system with three vertical Sulzer pumps driven by electric motors. This phase began during the third quarter of 2013.
In the second phase of the project, 390 kilometers (242 miles) of 36-inch pipeline will be installed from Banadia to Ayacucho. Also, a pump station will be built.
The third phase will consist of a 380-kilometer (236-mile), 36-inch pipeline from Ayacucho to Covenas, where tanks will be built at an existing Terminal (Covenas).
Progress on the last two phases included basic engineering, which was developed by the firm Inelectra Internacional (Bogotá, Colombia).
Project managers appear to be optimistic about the situation and expect to have all permits granted by mid-2015 in order to start public tender process.
View Plant Profile - 3042223 3042058 3042143
View Project Report - 300052463 300052467 300052526 300052523 300052529 300052322 300052321 300052520
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Petrobras Inaugurates Seven Platforms in 2013 for $11.5 Bill...December 30, 2013
-
Brownfield Expansions, Cleaner Fuels Lead Refining Projects ...October 15, 2026
-
Terremoto de magnitud 7,4 deja más de 100 muertos en Colombi...August 11, 2026
-
Earthquake Kills More Than 100 in Colombia; Key Refineries, ...August 11, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1, CDMO and ReshoringPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026