Caracoles Hydroelectric Project Reaches 68% Completion

Funds for this capital construction project were obtained through the contribution from the province of San Juan and the federal government.

Released Thursday, May 31, 2007

Caracoles Hydroelectric Project Reaches 68% Completion

Researched by Industrial Info Resources (Sugar Land, Texas). San Juan, an andine province of Argentina, is executing the “proyecto Caracoles,” which includes the construction of a dam and a hydroelectric power station. The undertaking is regarded as the most important power station currently built in Argentina due to its importance in balancing the energetic deficit by providing electricity to the province of San Juan and its surroundings.

Funds for this capital construction project were obtained through the contribution from the province of San Juan and the federal government. The Techint - Panedile joint venture has reached 68% construction completion with almost 1,000 people working in the hydroelectric complex. Completion is scheduled for the second quarter of 2008.

The new dam over the San Juan River, located 53 km from San Juan city will be equipped with two 65 MW Francis type turbines and a 43 Km /134 KV power transmission line linking Caracoles and San Juan city. Among other ancillary works are: consolidation and completion of basic engineering, detail engineering, supplier engineering review, procurement, civil works and electromechanical assembly, precommisioning and start-up.

The electromechanical phase began with the arrival of the Y branch (40 tons of equipment) from the Russian city of St Petersburg last May 22. These electromechanical components will conduct water through the adduction tunnel towards the turbine, inside the dam´s engine room. This is the most sensitive phase in the project since it involves detailing and precision works including setting up the equipment to allow for the transformation of hydric energy into electric energy. The water that will generate energy is going to circulate throughout the tunnel that runs through the middle of the mountain.

The tunnel’s final section has a 200 meter fall, and since there are two turbines, the steel Y branch is fundamental to regulate the water volume that reaches 90 cubic meters per second.

Industrial Info Resources (IIR) provides marketing communication services ranging from industrial database solutions to market forecasting, custom analytics, and specialty promotions that support high-level image campaigns.
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 39 + 8?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

PECWeb Global Market Intelligence Platform

Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.

Discover Pecweb

Get notifications from IIR News Intelligence

Click 'Sign Up' then 'Allow'