Furnas’ Energy Restrictions Postpone Power Plant Outages in Brazil

Brazil’s Mascarenhas de Morais Hydroelectric Power Plant has postponed the start date of planned maintenance outages because of energy restrictions imposed by Furnas Centrais Eletricas S.A. (Rio de Janeiro, Brazil)...

Released Wednesday, October 10, 2007

Furnas’ Energy Restrictions Postpone Power Plant Outages in Brazil

Researched by Industrial Info Resources (Sugar Land, Texas)--Brazil’s Mascarenhas de Morais Hydroelectric Power Plant has postponed the start date of planned maintenance outages because of energy restrictions imposed by Furnas Centrais Eletricas S.A. (Rio de Janeiro, Brazil). Mascarenhas (476 megawatts) often takes two of its 10 generating units offline simultaneously. Contrary to this, Mascarenhas authorities were forced to reschedule the outages and to reduce the number of them.

The main reason for Furnas’ restrictions is that modernization work is underway at other Furnas hydroelectric power plants in the Brazilian Mina Gerais State: UHE Luiz Carlos Barreto de Carvalho (1,050 MW) and UHE Furnas (1,216 MW).

The upgrade at UHE Luiz Carlos Barreto de Carvalho is being carried out by the consortium specially created for this project, Consorcio Fornecedor Luis Carlos Barreto de Carvalho. Currently, work is underway on UG 1 (175 MW Voith Turbine), which will be completed in November.

On the other hand, Furnas Hydroelectric Plant has already completed the modernization of UG 6 (152 Mw Nohab Unit), and the modernization of the remaining seven units is estimated to be completed in 2010. In both cases, the modernization includes the turbine and generator’s total recuperation and the plant’s digitization in order to increase the equipments reliability and the operational security.

Mascarenhas de Morais has already completed its unit’s modernization. Some units have been entirely upgraded and others have just been partly improved. The 10 units have been operating for more than 30 years and consequently had been reducing their energy production before the renewal took place, which extended their utility life for some more decades.

Furnas Centrais Eletricas S.A. has 11 hydroelectric power plants and two thermal plants in Brazil, totalizing 9,910 MW and 7,971 MW respectively.

View Plant Profile - 1056031 1074725 1074809

Industrial Info Resources (IIR) provides marketing communication services ranging from industrial database solutions to market forecasting, custom analytics, and specialty promotions that support high-level image campaigns.
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 48 + 6?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

PECWeb Global Market Intelligence Platform

Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.

Discover Pecweb

Get notifications from IIR News Intelligence

Click 'Sign Up' then 'Allow'