Power
Hebi Power Plant Unit Passes 168-Hour Trial Operation
The Phase III expansion project of the large-scale pithead power plant, built beside the former Hebi power plant by Hebi Fenghe Power Generation Company Limited ...
Released Thursday, October 18, 2007
Researched by Industrial Info Resources (Sugar Land, Texas)--Unit 1 of Hebi power plants Phase III passed its trial operation of 168 hours in central Chinas Henan Province on September 28, 2007, officially making the unit fit for commercial operation.
The Phase III expansion project of the large-scale pithead power plant, built beside the former Hebi power plant by Hebi Fenghe Power Generation Company Limited (Henan, China), is an important power construction project to the provinces 11th five-year plan (2006-10). The $600 million project is jointly invested by Henan Provincial Investment Corporation (Henan, China) (50%), Hebi Coal Industry (Group) Company Limited (Henan, China) (46%) and Hebi Economic Development and Investment Corporation (Henan, China) (4%). The project will be furnished with two 600-megawatt (MW) supercritical coal-fired units, along with a high-efficient electrostatic dust-removing device, a continuous-flue-gas-monitoring device and a desulfurization device, for a total installed capacity of 1,200 MW. The project will also carry out flue gas desulfurization reformation for the two 200-MW coal-fired units built in Phase I of Hebi power plant.
The projects construction officially began September 30, 2005. With the support from governments in various levels, Central China Power Grid and the provincial electric power company, the project has been carried out smoothly. The project company has established a special leading team to commission the project since the plants power supply was successfully put into operation. Tests on all subsections were completed as scheduled. Unit 1 of the Phase III expansion was then smoothly synchronized to the grid on September 9, 2007.
Industrial Info Resources (IIR) provides marketing communication services ranging from industrial database solutions to market forecasting, custom analytics, and specialty promotions that support high-level image campaigns.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
NextEra Eyes Strong Backlog, Data Center Hub StrategyOctober 23, 2026
-
Winter 2026-27 Outlook: Strong El Niño Expected to Shape Nor...October 23, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Mining Capital Spending 2026: Copper, Rare Earths, AluminumPodcast Episode / Oct 23, 2026
-
Brazil Critical Minerals 2027: Rare Earths, Lithium, CopperPodcast Episode / Oct 16, 2026
-
US Craft Labor Outlook 2026: Wages, Per Diems, Data CentersPodcast Episode / Oct 16, 2026
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026