Released on Thursday, September 09, 2021

Chemical Processing

IIR Top Chemical Processing News Today

Chevron Phillips Chemical is on schedule to perform an approximately 45-day turnaround of its 1.84 billion-pound-per-year 1592 Ethylene Unit in Baytown (Cedar Bayou), Texas, in early 2022. An exact start date has not been scheduled; however, the turnaround is expected to be completed during the first quarter of 2022.

Attachment

North America
Chevron Phillips Chemical is on schedule to perform an approximately 45-day turnaround of its 1.84-billion-pound-per-year 1592 Ethylene Unit in Baytown (Cedar Bayou), Texas, in early 2022. An exact start date has not been scheduled; however, the turnaround is expected to be completed during the first quarter of 2022.

Flint Hills Resources is in the process of shutting down its 1.54 billion-pound-per-year Propane Dehydrogenation (PDH) Unit in Houston, Texas, for minor maintenance. The plant is expected to be offline for seven days, with the restart on September 14.

Shintech Louisiana is in the process of restarting its 1.1 billion-pound-per-year ethylene unit in Plaquemine, Louisiana, after the plant was shut down on August 28 in preparation for Hurricane Ida.

International
LG Chemical Limited's approximately 2.55-billion-pound-per-year ethylene unit at its Yeosu Yongseong Chemicals Plant in South Korea resumed normal operations on August 30. The unit's production had been curtailed by 10% on August 3 due to market conditions.

Reliance Industries Limited is planning a 30-day maintenance turnaround of the 881.80-million-pound-per-year ethylene unit, which would begin March 17, 2023, at its Nagothane Chemical Complex in India. Expectations are to complete repairs and restart the unit by April 15, 2023.

LyondellBasell Industries NV remains on schedule to perform a 45-day planned turnaround of the 804 million-pound-per-year ethylene unit, beginning September 16, at its Pfaffenhofen Complex in Germany. Expectations are to complete repairs and restart the unit by October 30.

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, six offices in North America and 12 international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities. Follow IIR on: Facebook - Twitter - LinkedIn.
/news/article.jsp false
Share This Article
Want More IIR News?

Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 10 + 6?
Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Learn More
Industrial Project Opportunity Database and Project Leads

Get access to verified capital and maintenance project leads to power your growth.

Learn More
Industry Intel


Explore Our Coverage

Industries


  • Electric Power
  • Terminals
  • Pipelines
  • Production
  • Alternative Fuels
  • Petroleum Refining
  • Chemical Processing
  • Metals & Minerals
  • Pulp, Paper & Wood
  • Food & Beverage
  • Industrial Manufacturing
  • Pharmaceutical & Biotech

Trending Sectors


  • Data Centers
  • Semiconductors
  • Battery Supply Chain
  • Packaging
  • Nuclear Power
  • LNG
IIR Logo Globe

Site-wide Scheduled Maintenance for September 27, 2025 from 12 P.M. to 6 P.M. CDT. Expect intermittent web site availability during this time period.

×
×

Contact Us

For More Info!