McArthur River Zinc and Lead Mine's Phase III Expansion Nears Completion
The McArthur River zinc and lead mine's Phase III expansion is entering its final stage, after the mechanical works were completed in September 2013.
Released Tuesday, October 08, 2013
Reports related to this article:
Researched by Industrial Info Resources Australia (Perth, Australia)--The McArthur River zinc and lead mine's Phase III expansion is entering its final stage, after the mechanical works were completed in September 2013. Construction on the $300 million expansion has been ongoing since December 2012, with completion expected in early 2014. The McArthur River mine is one of Xstrata's (ASX:XTA) key zinc and lead assets, along with the George Fisher Mine in Mount Isa, Queensland.
The McArthur River Mine is 70 kilometres southwest of Borroloola in the Northern Territory and has been operational since 1995, with an estimated annual processing capacity of 2.5 million metric tons per year. The Phase III expansion is expected to increase the processing capacity to 5.5 million metric tons per year, producing approximately 380,000 tons per year of zinc and 93,000 tons per year of lead concentrate.
The project also involves the addition of a 53-megawatt (MW) gas power station, which will be constructed on a build, operate, own and maintain (BOOM) basis. The construction of the power station is expected to be completed by November 2013.
Due to the expansion, Xstrata had to expand the existing mining accommodation camp facility by another 364 "man camps" for the work force. The expansion on the accommodation village was completed in August 2013.
Engineering and project management firm Milestone Engineers (Perth) was appointed the engineering, procurement and construction (EPC) contractor for the expansion. The project also saw the involvement of other Western Australian contracting companies, such as Karridale Group and the Minserve Group. Engineering and technology firm Mipac Engineering was awarded a contract to install new control systems for the plant areas, such as dewatering, grinding, crushing and power stations. The Phase III expansion at McArthur River includes some of the surplus equipment from Xstrata's George Fisher mine in Mount Isa.
John Noordhoek, a project manager from Milestone Engineering, confirmed that the new equipment is scheduled to undergo final commissioning by November 2013, with minimum interference to the existing plant, and final completion by February 2014.
View Plant Profile - 1069346
View Project Report - 300051663 300052010 300052017
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Construction Under Way on McArthur River Mine Power StationMarch 11, 2013
-
Power Plant at McArthur River Mine Heads Toward ConstructionNovember 16, 2012
-
Peru's Government Expects US$7 Billion in Mining Investments...September 28, 2026
-
Glencore Eyes Growth at North American Copper, Nickel MinesAugust 21, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1, CDMO and ReshoringPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026