North Dakota Lignite Mine, Mine-Mouth Power Plant on Again
An elaborate enclosed conveyor belt system will be used to transport the coal from the mine to the power plant with great care to keep the coal dust at a minimum.
Released Wednesday, October 17, 2007
Researched by Industrial Info Resources (Sugar Land, Texas)--Westmoreland Coal Company (Colorado Springs, Colorado) plans to upgrade and restart a lignite coal mine with a capacity of 3 million-5 million tons per year in Gascoyne, North Dakota. Lignite is often referred to as brown coal and is the lowest ranking of coals. It is used almost exclusively as a fuel for steam-electric power generation. It has high natural moisture content and very high ash content when compared to bituminous coal. The heat content of lignite ranges from 9 million to 17 million British thermal unit(Btu)/ton, or 10 to 20 megajoules (MJ) per kilogram (kg) compared with the heat content of bituminous coal, which ranges from 21 million to 30 million Btu/ton, or 24 to 35 MJ/kg. Because of lignites low energy level, its not cost-effective to transport it a great distance. Although it is not the best or the brightest of the coals, it can be the low preference for a closely seated power plant. Sometimes these mines are called mine-mouth mines for obvious reasons. Westmoreland Energy LLC, a division of Westmoreland Coal, has plans in the offing for a multi-million dollar, 500-MW coal-fired power plant to be built close to the lignite mine. It is employing the engineering expertise of Sargent & Lundy (Chicago, Illinois) for the power plant project.
The joint projects covering the coal mine and power plant have been in the works for a number of years. When the power plant was proposed in early 2001, it came with a price tag of more than $700 million as a joint venture with the Montana-Dakota Utilities Company. The projects cost has since risen to approximately $1 billion and is no longer a joint venture but a wholly owned project by Westmoreland Energy LLC. The coal-mine proposal followed shortly after, along with its own price tag of $50 million. The cost for the restart and upgrades has risen over the years to about $120 million.
The site, outside of Gascoyne, North Dakota, is a former mining operation that started in 1946. It was called the Peerless Mine until in 1950, Knife River Coal purchased the mine and renamed it the Gascoyne Mine. In 1995, Knife River Coal lost its major contract and ceased operations. When reopened, the mine is expected to employ about 100 people, and the power plant will add 50-60 people. The Gascoyne community has a population of 21, according to the 2006 U.S. Census Bureau. Its estimated that the mine has a lignite reserve of 63.5 million tons. That would be considered an adequate supply for many years of operations.
View Plant Profiles - 1055550 1056045
View Project Reports - 31000203 31000362
Industrial Info Resources (IIR) provides marketing communication services ranging from industrial database solutions to market forecasting, custom analytics, and specialty promotions that support high-level image campaigns.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Isaias Forecast to Become First Hurricane of 2026 as Gulf En...October 07, 2026
-
KGHM, South32 Advance Sierra Gorda Copper Mine Expansion as ...October 07, 2026
-
Cornwall Lithium to Boost U.K. Critical Minerals PushOctober 07, 2026
-
KGHM y South32 avanzan en la expansión de la mina de cobre S...October 07, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1 Drives CapexPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026
-
2026 Global Power Demand Outlook: Gas, Nuclear & RenewablesPodcast Episode / Sep 18, 2026
-
2026 Oil & Gas CapEx Outlook: Middle East, LNG & PermianPodcast Episode / Sep 4, 2026