Power
Palo Verdes Unit Three Prepares for Refueling and Up-rated Capacity Outage
This increase will be achieved largely through the addition of two new steam generator/LP rotors sets, as well as a number of hardware change-outs to increase...
Released Wednesday, September 19, 2007
Researched by Industrial Info Resources (Sugar Land, Texas). In less than two weeks (September 29), the Palo Verde Nuclear Power Station will take their number three unit offline for its 18 month refueling outage, as well as performing hardware replacements for an up-rate in generating capacity. The up-rate has been determined to be 2.9% by the Nuclear Regulatory Commission (NRC) , boosting summer capacity (highest attainable yield) to 1,317 megawatts, the same increase in capacity percentage as was gained on the number one unit in 2005.
The plant is located about 35 miles west of Phoenix in Tonopah, Arizona, and has been the largest nuclear power producer in the United States since the mid-80s. Its three units are capable of generating over 3,900 megawatts of electricity, enough to power over three million average homes. Palo Verde is operated by Arizona Public Service Company (APS), and owned by a consortium of seven utilities in the Southwest. APS is the largest stakeholder in the generating facility at 29.1%.
View Plant Profile - 1015283
View Outage Report - 38019
Industrial Info Resources (IIR) provides marketing communication services ranging from industrial database solutions to market forecasting, custom analytics, and specialty promotions that support high-level image campaigns.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Europe Makes its First SMR InvestmentOctober 14, 2026
-
Fervo Starts Up 33-MW Utah Geothermal Power Plant UnitOctober 13, 2026
-
Ecuador to Cut Taxes on Imported Power Generation, Storage E...October 13, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1, CDMO and ReshoringPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026