Released February 28, 2014 | BEIJING
en
Researched by Industrial Info Resources China (Beijing, China)--Shandong Electric Power Construction No.2 Company (SEPCO2) (Jinan, Shandong), a subsidiary of Power Construction Corporation of China (PowerChina) (Beijing), kicked off the foundation excavation for the main powerhouse for Unit 1 of Datang Binzhou Power Generation Company Limited's (Binzhou, Shandong) 700-megawatt (MW) cogeneration power project on February 20, 2014. The project has entered its construction stage, according to an announcement from PowerChina on February 24.
The project is located in the Bincheng district of Binzhou City, in northern China's Shandong province. The project is invested by Datang Shandong Power Generation Company Limited (Jinan, Shandong), a regional subsidiary of China Datang Corporation (Beijing). The project received preliminary approval from the National Energy Administration to kick off pre-stage preparation in November 2011. According to the approval, the project will be furnished with two 350-MW, supercritical, combined-heat-and-power units, with a total investment of about $450 million in the current stage.
Through public bidding, SEPCO2 won the main construction contract in Bid A, which includes the construction of Unit 1, as well as the centralized control building; startup boiler room; fuel oil system; ash-conveying system (including the ash storage); air-compressor system; erection of the first heat supply station, as well as associated pipeline works; and the construction of the step-up substation.
Beijing Electric Power Construction Company Limited (Beijing), a subsidiary of China Energy Engineering Corporation (CEEC) (Beijing), is responsible for the construction of Unit 2 (Bid B). As the winner of Bid C and Bid D, Shandong Electric Power Construction No.1 Company (SEPCO1) (Jinan, Shandong) is responsible for the construction of the chimney structure (Bid C), and the construction of the cooling towers, circulation water pump room, and circulating water pipeline works (Bid D).
The main turbine, generator and boiler equipment for the project is to be supplied by Harbin Electric Corporation (Harbin, Heilongjiang). Shandong Electric Power Engineering Consultation Institute (SEPECI) (Jinan, Shandong) is responsible for the design and engineering of the project.
According to the schedule, the first concrete placement for the unit is expected to begin on March 15, 2014, and the unit will begin commercial operations on July 15, 2015.
View Project Report - 300023498
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
The project is located in the Bincheng district of Binzhou City, in northern China's Shandong province. The project is invested by Datang Shandong Power Generation Company Limited (Jinan, Shandong), a regional subsidiary of China Datang Corporation (Beijing). The project received preliminary approval from the National Energy Administration to kick off pre-stage preparation in November 2011. According to the approval, the project will be furnished with two 350-MW, supercritical, combined-heat-and-power units, with a total investment of about $450 million in the current stage.
Through public bidding, SEPCO2 won the main construction contract in Bid A, which includes the construction of Unit 1, as well as the centralized control building; startup boiler room; fuel oil system; ash-conveying system (including the ash storage); air-compressor system; erection of the first heat supply station, as well as associated pipeline works; and the construction of the step-up substation.
Beijing Electric Power Construction Company Limited (Beijing), a subsidiary of China Energy Engineering Corporation (CEEC) (Beijing), is responsible for the construction of Unit 2 (Bid B). As the winner of Bid C and Bid D, Shandong Electric Power Construction No.1 Company (SEPCO1) (Jinan, Shandong) is responsible for the construction of the chimney structure (Bid C), and the construction of the cooling towers, circulation water pump room, and circulating water pipeline works (Bid D).
The main turbine, generator and boiler equipment for the project is to be supplied by Harbin Electric Corporation (Harbin, Heilongjiang). Shandong Electric Power Engineering Consultation Institute (SEPECI) (Jinan, Shandong) is responsible for the design and engineering of the project.
According to the schedule, the first concrete placement for the unit is expected to begin on March 15, 2014, and the unit will begin commercial operations on July 15, 2015.
View Project Report - 300023498
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.