Canadian Natural Resources Limited, on May 14, began a 45-day planned plant-wide maintenance turnaround at its 144,000-barrel-per-day (BBL/d) Fort McMurray Oil Sands Upgrader (Horizon Oil Sands) in Alberta, Canada.
International
LUKOIL-Permnefteorgsintez is performing planned maintenance on the 38,100-BBL/d ABT-1 (Crude 1) and 22,800-BBL/d ABT-1 (Vaccum 1) units at its 273,800-BBL/d Perm Refinery in Russia. Completion is expected by the end of May. Meanwhile, maintenance on the 10,400-BBL/d Catalytic Cracker KK-1 unit is ongoing and is expected to be completed in early June.
Cosmo Oil Company Limited, today May 18, began a planned turnaround of the 102,000-BBL/d Crude 2 unit at its 177,000-BBL/d Chiba Refinery in Japan. The restart is expected by May 27. Meanwhile, maintenance on the 36,000-BBL/d Residual Hydrotreater 10 is ongoing, and the restart is scheduled for June 15.
Jordan Petroleum Refinery Company Limited (JPRC) continues with an unplanned shutdown of the 17,900-BBL/d Crude Distillation Unit (CDU) 1, 12,300-BBL/d CDU 2 and 4,500-BBL/d Fluid Catalytic Cracker Unit (FCCU) at its 105,000-BBL/d Zarqa Refinery in Jordan. The units remain offline following the completion of a 57-day maintenance shutdown on February 28, and are tentatively expected to restart by July 15.
Industrial Info Resources (IIR) is the world's leading provider of market intelligence across the upstream, midstream and downstream energy markets and all other major industrial markets. IIR's Global Market Intelligence Platform (GMI) supports our end-users across their core businesses, and helps them connect trends across multiple markets with access to real, qualified and validated project opportunities. Follow IIR on: LinkedIn.
Canadian Natural Resources Limited, on May 14, began a 45-day planned plant-wide maintenance turnaround at its 144,000-barrel-per-day (BBL/d) Fort McMurray Oil Sands Upgrader (Horizon Oil Sands) in Alberta, Canada.
International
LUKOIL-Permnefteorgsintez is performing planned maintenance on the 38,100-BBL/d ABT-1 (Crude 1) and 22,800-BBL/d ABT-1 (Vaccum 1) units at its 273,800-BBL/d Perm Refinery in Russia. Completion is expected by the end of May. Meanwhile, maintenance on the 10,400-BBL/d Catalytic Cracker KK-1 unit is ongoing and is expected to be completed in early June.
Cosmo Oil Company Limited, today May 18, began a planned turnaround of the 102,000-BBL/d Crude 2 unit at its 177,000-BBL/d Chiba Refinery in Japan. The restart is expected by May 27. Meanwhile, maintenance on the 36,000-BBL/d Residual Hydrotreater 10 is ongoing, and the restart is scheduled for June 15.
Jordan Petroleum Refinery Company Limited (JPRC) continues with an unplanned shutdown of the 17,900-BBL/d Crude Distillation Unit (CDU) 1, 12,300-BBL/d CDU 2 and 4,500-BBL/d Fluid Catalytic Cracker Unit (FCCU) at its 105,000-BBL/d Zarqa Refinery in Jordan. The units remain offline following the completion of a 57-day maintenance shutdown on February 28, and are tentatively expected to restart by July 15.
Industrial Info Resources (IIR) is the world's leading provider of market intelligence across the upstream, midstream and downstream energy markets and all other major industrial markets. IIR's Global Market Intelligence Platform (GMI) supports our end-users across their core businesses, and helps them connect trends across multiple markets with access to real, qualified and validated project opportunities. Follow IIR on: LinkedIn.