With new plants scheduled to be built, a brand spanking new one is in its final phase of completion. Constructed in 2005, Ross Management’s 14-megawatt Tieton Hydro Power Station is...

Released Thursday, May 04, 2006

Washington Hydro Owners Continue to Invest Millions on New Development and Plant Upgrades

Researched by Industrial Info Resources (Sugar Land, Texas). Of all the renewable energy sources, such as solar, wind, geothermal and biomass, that generate electricity, hydroelectric power is the oldest and largest contributor. Over one half of the total U.S. hydroelectric capacity for electric generation is concentrated in three states: Washington, California, and Oregon. While maybe not as topical as other developing renewable technologies, there is a substantial amount of project work to expand and replace the nation's aging hydroelectric fleet.

For example, Puget Sound Energy (Bellevue, Washington) plans to invest approximately $35 million to install two additional 25-megawatt hydro turbine/generator sets to its 70-megawatt Lower Baker River Hydro Power Station (Concrete, Washington). Preliminary design is still being developed on the 2010 project. A design firm will be chosen later this year and completion is scheduled for 2012.

The Public Utility District of Grant County (Beverly, Washington) will spend $250 million to upgrade its Priest Rapids Hydro Power Station (Othello, Washington) starting in 2008. The project scope is to replace ten 91-megawatt turbines with a more efficient, fish-friendly design plus perform upgrades to the generators, as is currently being done at its Wanapum Hydro Power Station (Beverly, Washington) (see related article on March 1, 2006 - West Coast power producers to spend $800-million on hydroelectric plant upgrades).

With new plants scheduled to be built, a brand spanking new one is in its final phase of completion. Constructed in 2005, Ross Management’s (Goldendale, Washington) 14-megawatt Tieton Hydro Power Station is scheduled to be operational sometime this summer.

View Plant Profile – 1500733 1505431 1063861 1015136 1511106
View Project Report – 21000459 21001414 21001274 21001265 21001274 21001174

Industrial Info Resources (IIR) is a Marketing Information Service company that has been doing business for over 23 years. IIR is respected as the leader in providing comprehensive market intelligence pertaining to the industrial processing, heavy manufacturing, and energy-related industries throughout the world.
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 28 + 4?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

PECWeb Global Market Intelligence Platform

Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.

Discover Pecweb

Get notifications from IIR News Intelligence

Click 'Sign Up' then 'Allow'