The stay ring in the first unit of Huaneng Tibet Power Generation Company Limited's Zangmu Hydropower Station was erected into its final position on June 25, 2013
Released Monday, July 08, 2013
Reports related to this article:
Researched by Industrial Info Resources China (Beijing, China)--The stay ring in the first unit of Huaneng Tibet Power Generation Company Limited's (Chengdu, Sichuan) Zangmu Hydropower Station was erected into its final position on June 25, 2013. The mechanical erection for the project has kicked off, according to an announcement from China Huaneng Group (Beijing) on June 28, 2013.
The stay ring is a benchmark in the erection of the hydraulic turbine generating unit and the first large piece to be erected after the kickoff of construction. In order to ensure the smooth and safe erection of the stay ring, Huaneng Tibet held several coordination, safety and technical clarification meetings prior to the erection. The erection was performed safely and accurately following repeated reviews on site conditions, the lifting scheme and related preparation.
The Zangmu Hydropower Station, located in the middle reaches of Yaluzangbu River in Jiacha County, Shannan prefecture, in the Tibet autonomous region, is the first large-scale hydropower station in Tibet. The project mainly comprises a 116-meter-high gravity dam with a maximum storage capacity of 86.6 million cubic meters under a normal pool level of 3,310 meters above sea level, and a river-bed type powerhouse furnished with six units, each of 85 MW. The total installed capacity is 510 megawatts (MW).
The project received approval from the National Development and Reform Commission (NDRC), the top planner in China, in July 2010. The river diversion of the project was completed in November 2010. Construction of the project then kicked off at the end of 2010. According to the schedule, the first unit of the project is expected to begin operations in 2014, and all six units of the project will be commissioned in 2016. Upon completion, the project will be the largest hydropower station in Tibet and will be able to produce about 2.5 billion kilowatt-hours of clean energy to the Tibet grid, which will effectively alleviate the power shortage in Tibet and will promote its social and economic development.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Global Power Construction Spending Led by Nuclear, WindAugust 24, 2026
-
Join Industrial Info for a Power Industry WebinarSeptember 23, 2024
-
Ethiopia Aims for Additional 17 GW of Renewable Energy by 20...September 12, 2024
-
Argentina Weighs Natural Gas Pipeline Venture with ChinaJune 09, 2023
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Mining Capital Spending 2026: Copper, Rare Earths, AluminumPodcast Episode / Oct 23, 2026
-
Brazil Critical Minerals 2027: Rare Earths, Lithium, CopperPodcast Episode / Oct 16, 2026
-
US Craft Labor Outlook 2026: Wages, Per Diems, Data CentersPodcast Episode / Oct 16, 2026
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026