Mighty River Power Limited has completed the 82-megawatt Ngatamariki Geothermal Power Plant near Taupo, New Zealand. The power plant is 'an important new asset for the company.'
Released Wednesday, September 11, 2013
Reports related to this article:
Project(s): View 1 related project in PECWeb
Plant(s): View 1 related plant in PECWeb
Researched by Industrial Info Resources (Perth, Australia)--Mighty River Power Limited (Auckland, New Zealand) has completed the 82-megawatt (MW) Ngatamariki Geothermal Power Plant near Taupo, New Zealand. Located approximately 17 kilometres northeast of Taupo, the power plant is "an important new asset for the company," said Doug Heffernan, the chief executive officer of Mighty River Power.
The power plant has three production geothermal wells and four re-injection wells, along with 21 sentinel and monitoring wells, with a total depth of 40 kilometres. The Ngatamariki station is considered a valuable asset for the company; it is designed to operate as a base load station, producing about 700 gigawatt-hours of electricity annually, which is the equivalent of supplying electricity to approximately 80,000 households.
This project, the largest of its type in the world, took 21 months to complete. With a peak workforce of about 450 persons on site, the project involved more than 1 million man-hours on construction, from initial earthworks to the handover.
Mighty River contributes 17% of New Zealand's electricity needs through multiple channels and retail brands, including Mercury Energy, GLO-BUG, Bosco Connect and Tiny Mighty Power. About 90% of the electricity is generated utilizing a diverse range of renewable hydro and geothermal energy stations.
The addition of the Ngatamariki will increase this contribution to more than 40% of the company's total renewable energy generation. Actual project construction was completed by June, and July and August involved testing and fine-tuning the individual units, as well as the overall plant, to check the variation of the units' total output.
Mighty River Power has geothermal permits to expand the power station capacity to 40 MW. However, the company will run the existing power station and study the geothermal resource capacity of the site to develop the expansion project.
View Plant Profile - 3029391
View Project Report - 300041969
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Learn MoreRelated Articles
-
Mighty River Power Expands New Zealand's Portfolio with Majo...January 25, 2013
-
Mighty River Begins $500 Million Modernization and Refurbish...December 31, 2013
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Learn MoreIndustry Intel
-
2026 Regional Chemical Processing OutlookOn-Demand Podcast / Mar. 2, 2026
-
From Data to Decisions: How IIR Energy Helps Navigate Market VolatilityOn-Demand Podcast / Nov. 18, 2025
-
Navigating the Hydrogen Horizon: Trends in Blue and Green EnergyOn-Demand Podcast / Nov. 3, 2025
-
ESG Trends & Challenges in Latin AmericaOn-Demand Podcast / Nov. 3, 2025
-
2025 European Transportation & Biofuels Spending OutlookOn-Demand Podcast / Oct. 27, 2025