CEEC Completes First Concrete Placement for Zheneng Group's Liuheng Coal-Fired Power Plant
Zhejiang Thermal Power Construction Company Limited recently completed the placement of the first bucket concrete for the boiler room foundation of the Zheneng Liuheng...
Released Thursday, August 09, 2012
Researched by Industrial Info Resources China (Beijing, China)--Zhejiang Thermal Power Construction Company Limited (Hangzhou, Zhejiang), a subsidiary of China Energy Engineering Corporation (CEEC) (Beijing), recently completed the placement of the first bucket concrete for the boiler room foundation of the Zheneng Liuheng coal-fired power plant. The company is the construction contractor for the project. This means that the construction for the main works of the first "offshore type," large-scale, coal-fired power plant has kicked off, according to an announcement from the CEEC on August 3, 2012.
The Zheneng Liuheng coal-fired power plant is located at Liuheng Island of Putuo District in Zhoushan City, in the Zhejiang province. The power plant has a total planned capacity of 4,000 megawatts (MW). Two 1,000-MW, ultra-supercritical, coal-fired units, together with a high-efficiency electrostatic dust remover, flue gas desulfuration and nitrogen oxide control devices, will be built in Phase I with a total investment of about $1.2 billion.
Zhejiang Zheneng Sinocoal Zhoushan Coal & Electricity Company Limited, a subsidiary of Zhejiang Provincial Energy Group (Hangzhou, Zhejiang) with joint investment from China National Coal Corporation (Beijing), is responsible for the development and future operation of the project. Zhejiang Electric Power Design Institute (Hangzhou, Zhejiang) is responsible for the design and engineering of the project.
The project received approval from the National Development and Reform Commission in January 2011. Site preparation of the project kicked off in May 2011. Beijing Babcock & Wilcox Company Limited (Beijing) and Dongfang Electric Corporation Limited (Chengdu, Sichuan) will supply the required boilers and steam turbine generator units, respectively, to the project.
As the first "offshore type" island coal-fired power plant in China, the project, together with the coal storage port in Zhoushan, forms an important coal and power-integrated project in the Zhejiang province. So far, the coal storage port has been put into operation. According to the latest schedule, the first unit of the project will begin operations in June 2014, and the second unit in October 2014.
View Project Report - 300032937
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Discover Our DatabaseIndustry Intel
-
The Role of Contract Manufacturing in Global Pharma GrowthPodcast Episode / May 8, 2026
-
2026 North American Labor OutlookPodcast Episode / Apr 24, 2026
-
2026 European Metals & Minerals Project Spending OutlookPodcast Episode / Apr 7, 2026
-
The Age of Critical Minerals in the AmericasPodcast Episode / Mar 20, 2026
-
2026 Regional Chemical Processing OutlookPodcast Episode / Mar 6, 2026