Join us on January 28th for our 2026 North American Industrial Market Outlook. Register Now!
Sales & Support: +1 800 762 3361
Member Resources
Industrial Info Resources Logo
Global Market Intelligence Constantly Updated Your Trusted Data Source for Industrial & Energy Market Intelligence
Home Page

Advanced Search

Reports related to this article:


Released May 19, 2014 | BEIJING
en
Researched by Industrial Info Resources China (Beijing, China)--A panel has cleared the way for a grid connection plan for Henan Zhoukou Longda Power Generation Company Limited's (Zhoukou, Henan) 1,200-megawatt (MW) expansion project at the Shangshui Power Plant. The panel, organized by the Henan Development and Reform Commission and Henan Electric Power Company Limited (Zhengzhou, Henan), approved the plan on May 8, allowing preparations for the expansion project to proceed, according to the project designer, Henan Electric Power Design Institute (Zhengzhou, Henan).

The Shangshui Power Plant is located in Zhoukou City, Shangshui County, in central China's Henan province, where the Henan electric grid currently has a weak connection to the provincial grid. The expansion project includes the installation of two 600-MW steam turbine generators to meet the growing power requirements of the area. The two existing 135-MW units at the plant have been shut down.

The project is scheduled to kick off at the beginning of 2015. Both units would begin operations by the end of 2016, replacing small, coal-fired units that generate 462 MW. The feasibility study for the expansion project was approved in January 2013.

View Plant Profile - 3016800
View Project Report - 300023010

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and 10 international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
IIR Logo Globe

Site-wide Scheduled Maintenance for September 27, 2025 from 12 P.M. to 6 P.M. CDT. Expect intermittent web site availability during this time period.

×
×

Contact Us

For More Info!