Metals & Minerals
Lundin's Caserones Mine Faces Up to Three-Week Restart Following Storm Damage
The Caserones copper mine in Chile faces a two- to three-week restart time after severe weather damaged power infrastructure.
Released Tuesday, July 28, 2026
Reports related to this article:
Written by Amir Richani for IIR News Intelligence (Sugar Land, Texas)
Summary
Lundin's Caserones mine has been without power since July 18, with power restoration and the gradutial restart of operations expected to take between two to three weeks.No Power
Lundin said on July 27 that its Caserones copper mine in Chile's Atacama region has been without power since July 18, after severe weather brought heavy rainfall and snowfall, forcing the company to suspend operations.The company has started backup generators to support critical infrastructure at the site. Lundin identified damage to two power line towers serving the mine, and has since deployed crews to repair the damage. Power restoration and the gradual restart of operations are expected over the next two to three weeks.
Industrial Info Resources data show three active projects at the Caserones mine involving US$150 million in investments for new equipment and expansions.
Despite the disruption, the company said on July 21 that it has incorporated weather disruptions into its production forecasts and maintains full-year production guidance at Caserones of 130,000 to 140,000 tonnes of copper. No update for the production forecast was issued on July 27.
During the first quarter, the Caserones mine was Lundin's largest copper producer, with output of 39,000 tonnes or 48.2% of the company's volumes.
Lundin completed the acquisition of an additional 5% interest in Caserones in April, increasing its ownership in the mine to 75%.
Candelaria Mine Disruption
Lundin also reported a brief disruption of its operations at its Candelaria mine due to severe weather in Chile's Atacama. However, the mill continued to operate using existing stockpiles, while mining has since returned to full capacity.The Candelaria mine recorded volumes of 31,000 tonnes of copper in first-quarter 2021, and its guidance for the year has been set at 135,000 to 145,000 tonnes of copper.
Industrial Info Resources is tracking 40 projects at the Candelaria mine worth slightly more than US$1 billion.
Copper Prices
The disruption comes as the copper market remains sensitive to pottential supply disruptions amid high prices. Over the last week, copper prices have remained above the US$6-per-pound mark, driven by nine-month-high Chinese imports, low inventories in London and Shanghai, lower production from Chilean mines, and solid long-term demand for the red metal, according to Cochilco, the Chilean Copper Agency.Demand for copper is expected to remain strong over the next few years, driven by the transition to renewable energy as well as grid expansion, both copper-intensive.
Key Takeaways
- Power supply and operations at the Caserones copper mine have been impacted since July 18 due to severe weather.
- The company expects to restart operations in the next two to three weeks.
- The Candelaria mine also had operations impacted by severe weather, though the company has since restarted production.
About Industrial Info Resources
Industrial Info Resources (IIR) is the leading provider of industrial market intelligence. Since 1983, IIR has provided comprehensive research, news and analysis on the industrial process, manufacturing and energy related industries. IIR's Global Market Intelligence (GMI) helps companies identify and pursue trends across multiple markets with access to real, qualified and validated plant and project opportunities. Across the world, Industrial Info Resources is tracking over 250,000 current and future projects worth $30.2 trillion (USD).
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
La minera de cobre Lundin cierra otro trimestre con una sóli...November 12, 2025
-
Copper Miner Lundin Surpasses Output ExpectationsNovember 10, 2025
-
Lundin Mining Vows to Become a Top-10 Copper ProducerJune 20, 2025
-
Lundin's Candelaria Mine in Chile Gets Lifetime Extension Ap...September 14, 2023
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
European Chemicals and Transport Fuels OutlookPodcast Episode / Jul 10, 2026
-
2026 European Petroleum Refining Project OutlookPodcast Episode / Jun 26, 2026
-
Brazil: Efficiency, Innovation, and Opportunities in the Food & Beverage IndustryPodcast Episode / Jun 12, 2026
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026