Unit 6 of Guodian Baoji No. 2 Power Plant Expansion Begins Operations
Unit 6, the second 660-megawatt unit at Guodian Baoji Power Generation Company Limited's Baoji No. 2 Power Plant expansion project, passed the 168-hour, continuous full-load trial ...
Released Friday, January 13, 2012
Researched by Industrial Info Resources China (Beijing, China)--Following the successful commissioning of the 660-megawatt (MW) Unit 5 on February 17, 2011, Unit 6, the second 660-MW unit at Guodian Baoji Power Generation Company Limited's (GBPGC) (Baoji, Shaanxi) Baoji No. 2 Power Plant expansion project, passed the 168-hour, continuous full-load trial operation on December 31, 2011. During the trial operation, various technical indicators were rated at the "excellent" level. The Guodian Baoji No. 2 Power Plant Phase II Expansion Project was completed, China Guodian Corporation (Beijing) announced on January 5, 2012.
The Guodian Baoji No.2 Power Plant is in Changqing Town, which is about 28 kilometers from downtown Baoji. The power plant was built in October 1996, with four 300-MW units commissioned in December 1998, November 1999, September 2000 and March 2001, respectively. The expansion project was built on the reserved space of Phase I, with joint investment from China Guodian Corporation (Beijing) (65%) and Shaanxi Investment Group Company Limited (Xi'an, Shaanxi) (35%). The expansion project is furnished with two 660-MW, Chinese-made, supercritical, air-cooling, coal-fired units, with the adoption of a cooling tower, desulfuration tower, and a chimney "three-in-one" scheme, the first of its kind in China. The Northwest Electric Power Design Institute (Xian, Shaanxi), a regional subsidiary of China Power Engineering Consulting Corporation (Beijing), is responsible for the design and engineering of the project. Northwest Electric Power Construction Group Company Limited (Xi'an, Shaanxi) is responsible for the construction and installation of the project.
Construction of the project began in 2009. However, final approval of the project was not received from the National Development and Reform Commission (NDRC) until August 24, 2010. With the commissioning of the expansion project, the total installed capacity of Guodian Baoji No.2 Power Plant has been increased to 2,530 MW. The plant will play a more important role in the northwest grid and will serve as a good example in the sector due to its unique features.
View Project Report - 88001353
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Data Centers Push Vistra to Grow U.S. Nuclear, Natural Gas F...August 25, 2026
-
Typhoon Saudel Threatens Okinawa, Eastern ChinaAugust 25, 2026
-
DOE Seeking Loan Applicants for U.S. Energy Projects Favored...August 25, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
European Chemicals and Transport Fuels OutlookPodcast Episode / Jul 10, 2026
-
2026 European Petroleum Refining Project OutlookPodcast Episode / Jun 26, 2026
-
Brazil: Efficiency, Innovation, and Opportunities in the Food & Beverage IndustryPodcast Episode / Jun 12, 2026
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026