University of Memphis Investing $36 Million on Quintet of Infrastructure Projects
The largest of these projects is the proposed $15 million Law School relocation utilities project. As part of the relocation of the universitys Law School...
Released Thursday, February 01, 2007
Researched by Industrial Info Resources (Sugar Land, Texas). Your average university campus is one that is constantly evolving and changing. Each year, new classes and fields of study are added to the curriculum while others are dropped. As a result of the never-ending evolution of a university, the administration is constantly involved in renovating the physical facilities that make up that university. Each year, hundreds of millions of dollars are allocated to constructing new administration buildings, classrooms, dormitories, research centers and the infrastructure that supports all of the aforementioned. Currently, the University of Memphis (Memphis, Tennessee) is intending to invest $36 million on a quintet of infrastructure-related projects across its campus that will support all of its academic facilities.
The second largest project is really two projects: phase I and II of a central plant expansion. Combined, these projects weigh in at $13 million; $6 million for phase I and $7 million for phase II. The first phase of the project will involve the construction of a 3,750 square-foot building (50x75), the construction of a chilled water loop to service three to four buildings and the replacement of all of the three-way valves on the air handles in 50+ buildings that currently use two-way valves (there are approximately ten air handlers per building). SSR Ellers, Incorporated (Memphis, Tennessee) is the engineer on the first phase and is currently, in conjunction with the university, completing the engineering and preparing to begin the contracting next month. The building construction is scheduled to begin in May, with the chilled water loop and air handler portions of the project beginning in September of this year. Phase I will be complete by the end of the year.
Phase II will involve the installation of a pair of 1,400-ton chillers in the newly constructed building (part of phase I). A design firm will be selected in the fall of 2007, with the general contractor selection currently scheduled for early in 2008. Actual construction is expected to begin during the summer of 2008, with the project being complete in early 2009.
The fourth infrastructure project the university is currently working on is the South campus electrical system project. This $5 million project will involve the replacement of the existing antiquated 4,160V electrical distribution system across the South campus with a new 12.4kV system as well as the addition of a new substation/switching station. SSR Ellers, Incorporated is also the engineer on this project as well. Current schedules call for the selection of a general contractor in October of this year, with equipment procurement and subcontractor selection beginning shortly thereafter. Construction is expected to begin in the spring of 2008, with the project being complete by the end of the year.
The final project is the proposed $3 million University Center utilities replacement project. As part of the demolition and replacement of the 172,000 square-foot University Center, the university will install one new 800-ton chiller and a single 100,000 lbs/hr natural gas-fired boiler to provide for its chilled water and steam needs. Fisher & Arnold (Memphis, Tennessee) has been selected to provide engineering services and Inman Construction Corporation will be the general contractor on the project. Equipment procurement and subcontractor selection will begin in July of this year, with actual construction slated to begin in October. The project is anticipated to be complete in the early spring of 2008.
The University of Memphis was established by the General Education Bill enacted by the Tennessee legislature in 1909 and was founded in 1912 as the West Tennessee State Normal School. Situated on 1,160 acres and playing host to 202 buildings, the university has a current enrollment of over 20,500, an annual operating budget of $344 million, and employs approximately 2,500.
View Plant Profile 1061525
View Project Report 25002196 25002198 25002199 25002200 25002202
Industrial Info Resources (IIR) provides marketing communication services ranging from industrial database solutions to market forecasting, custom analytics, and specialty promotions that support high-level image campaigns.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
August Wildfire Outlook Expands Risk Across U.S. Energy Regi...August 11, 2026
-
Something in the Air: Construction at U.S. Missile Plants A...August 11, 2026
-
Trump Places Tariffs on Key Material for Solar Panels, Semic...August 10, 2026
-
DOI Plan Would Cut Colorado River Water Allocations for Ariz...August 07, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
European Chemicals and Transport Fuels OutlookPodcast Episode / Jul 10, 2026
-
2026 European Petroleum Refining Project OutlookPodcast Episode / Jun 26, 2026
-
Brazil: Efficiency, Innovation, and Opportunities in the Food & Beverage IndustryPodcast Episode / Jun 12, 2026
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026