Released June 11, 2020 | Cordoba, Argentina
en
Bolivian refiner Yacimientos Petrolíferos Fiscales Bolivianos (YPFB) continues to struggle to improve production levels at its refineries. The 21,000-barrel-per-day (BBL/d) Guillermo Elder Bell Refinery is running at approximately 60% of total capacity, while the 38,500-BBL/d Gualberto Villarroel Refinery is at 55% capacity. YPFB was dealing with the same derated levels in May, which now are tentatively extended until late June if demand volume does not improve. The planned turnaround schedule for the Guillermo Elder Bell site remains in place for July, unless the company cannot meet the necessary staff to accomplish the work. Click here for the plant reports and see map below.