Preliminary Engineering Report for Pingwei Power Plant's 2,000-Megawatt Expansion Passes Examination
The internal examination meeting for the preliminary engineering report of Pingwei Power Plant's Phase III, 2,000-megawatt expansion project was held in Huainan...
Released Tuesday, July 17, 2012
Reports related to this article:
Researched by Industrial Info Resources (Sugar Land, Texas)--The internal examination meeting for the preliminary engineering report of Pingwei Power Plant's Phase III, 2,000-megawatt (MW) expansion project was held in Huainan City, in the Anhui province, from July 3 to 4, 2012, according to an announced from the East China Electric Power Design Institute (ECEPDI) (Shanghai) on July 5, 2012.
The Pingwei Power Plant, located in Pingwei Town, in Huainan City, was built in 1985. The power plant currently has four 600-MW, coal-fired units in operation. Of which, the first 600-MW, coal-fired unit was commissioned in November 1989.
The Phase III expansion project is invested by Anhui Huainan Pingwei Power Generation Company Limited (Huainan, Anhui), a fully owned subsidiary of China Power International, and will serve as the main power source for a program to transmit power from Anhui to eastern China.
In September 2011, the project received preliminary approval from the National Energy Administration, which allowed the project owner to kick off pre-stage preparation for the project. In November 2011, the invitation for bids on the supply of turbine, generator and boiler main equipment was issued. The contract for the supply of main equipment was then awarded in March 2012. According to the contract, Beijing Babcock & Wilcox Company Limited (Beijing) will supply two 3,280-ton-per-hour, ultra-supercritical, coal-fired boilers, as well as the selective catalyst reduction (SCR) system for the project.
Presently, the project owner is working with ECEPDI, the project designer, for the final approval of the project. According to the schedule, the project will begin construction later this year, and both units will begin operations in 2014.
Among the leaders and representatives who attended the meeting were Bai Jinchang, the general manager of China Power International Development Limited (Hong Kong), and Chen Zheng, the chief engineer of EDEPDI.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
APEC2 Begins Welding on Unit 5 of Expansion Project at Huain...September 16, 2013
-
EIA of Huaibei Pingwei Power Plant's Units 1-4 Nitrogen Oxid...December 21, 2012
-
China to Build Four Hualong One Nuclear Power Reactors in 20...January 31, 2019
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1, CDMO and ReshoringPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026