Power
CNECC Completes Dome Erection for Unit 1 of Haiyang Nuclear Power Project
China Nuclear Engineering Construction Corporation erected the containing vessel top head for Unit 1 of the Haiyang Nuclear Power Project onto its final position
Released Friday, April 05, 2013
Reports related to this article:
Researched by Industrial Info Resources China (Beijing, China)--China Nuclear Engineering Construction Corporation (CNECC) (Beijing) erected the containing vessel top head (CVTH) (also referred as the "dome") for Unit 1 of the Haiyang Nuclear Power Project onto its final position on March 29, 2013, according to an announcement from the CNECC on April 2.
As reported, the containing vessel for the Haiyang Nuclear Power Project comprises the inner steel vessel and the outer concrete powerhouse, and is capable of withstanding strong shocks, such as earthquakes or even the airplane crashes. The steel vessel is about 40 meters in diameter and about 60 meters in height, and has a total weight of about 3,000 metric tons. The CVTH is about 800 metric tons in weight.
Several members of the CNECC are involved in the construction of the Haiyang Nuclear Power Project. China Nuclear Industry Fifth Construction Company Limited (CNEC5) (Shanghai) is serving as the general contractor for construction; China Nuclear Industry No. 22 Engineering Company (CNI22) (Yichang, Hubei) is responsible for the civil construction. China Nuclear Industry Zhongyuan Company is responsible for the erection of heavy pieces.
The Haiyang Nuclear Power Plant is located at Liugezhuang Town in Haiyang City, in northern China's Shandong province. The power plant has a total planned capacity of six 1,000-megawatt (MW) nuclear power units, with space reserved for future expansion. Shandong Nuclear Power Company Limited (Yantai, Shandong), a joint venture under the control of China Power Investment Corporation (Beijing) (40%), with the participation of China Nuclear Power Corporation (Beijing) (20%), China Guodian Corporation (Beijing) (20%), China Huaneng Group (Beijing) (5%) and two other local power investors from Shandong and Yantai are responsible for the development and future operation of the project.
As a support project for the localization of the third generation of nuclear power units in China, Phase I of the project will be furnished with two 1,250-MW, AP-1000-based nuclear power units. Construction of Phase I kicked off on December 28, 2009. According to the schedule, the first unit of the project is expected to begin commercial operations in 2014.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
CNECC Completes Erection of All Four Gates for Unit 1 of CPI...November 26, 2012
-
Global Power Construction Spending Led by Nuclear, WindAugust 24, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
European Chemicals and Transport Fuels OutlookPodcast Episode / Jul 10, 2026
-
2026 European Petroleum Refining Project OutlookPodcast Episode / Jun 26, 2026
-
Brazil: Efficiency, Innovation, and Opportunities in the Food & Beverage IndustryPodcast Episode / Jun 12, 2026
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026