Marathon continues with a plant-wide maintenance turnaround, which began on February 27, at its 64,000-BBL/d Salt Lake City, Utah, refinery. The event is scheduled to be completed by April 2, when the units will be back online.
Released Wednesday, March 18, 2020
North America
Marathon continues with a plant-wide maintenance turnaround, which began on February 27, at its 64,000-BBL/d Salt Lake City, Utah, refinery. IIR has confirmed that the refinery was not impacted by an earthquake in the area early this morning. The turnaround is scheduled to be completed by April 2.
Consumer Co-Operative Refineries Limited will postpone a 40-day planned maintenance turnaround involving five units, which was scheduled for April 2, at its 130,000-BBL/d Regina, Saskatchewan, refinery, due to the COVID-19 virus. The turnaround now is expected to be performed on or around May 15.
Valero has suspended a 55-day major turnaround on the 170,000-BBL/d Crude 1, 32,000-BBL/d Reformer, 70,000 BBL/d Diesel Hydrotreater and 40,000-BBL/d Kerosene Hydrotreater units at its 265,000-BBL/d Jean Gaulin, Canada, refinery, due to concerns over the COVID-19 outbreak. The turnaround had been scheduled to start in early April 2020. A new turnaround date has not been established.
International
SK Energy Company Limited began a 27-day planned turnaround of the 40,000-BBL/d VRDS (Vacuum Residue Desulfurization) unit on March 18 at its 840,000-BBL/d Ulsan Nam-gu, South Korea, complex. Expectations are to complete repairs and resume normal operations by April 13.
Yanbu Aramco Sinopec Refining Company (YASREF) restarted its 400,000-BBL/d Yanbu Refinery in Saudi Arabia on March 15. The refinery had been under a planned maintenance shutdown since February 1.
Mangalore Refinery & Petrochemicals Limited (MRPL) has rescheduled a 25-day planned major maintenance turnaround of the Phase 2 block, which includes six major units, at its 300,000-BBL/d Mangalore Refinery in India due to the COVID-19 pandemic. The turnaround, which was planned to start March 20, is now planned to tentatively begin on April 15. Expectations are to complete repairs and restart the unit by May 9.
For more insight contact iirteam@iirenergy.com
www.iirenergy.com
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our Solutions
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
2026 European Petroleum Refining Project OutlookPodcast Episode / Jun 26, 2026
-
Brazil: Efficiency, Innovation, and Opportunities in the Food & Beverage IndustryPodcast Episode / Jun 12, 2026
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026
-
The Role of Contract Manufacturing in Global Pharma GrowthPodcast Episode / May 8, 2026