JEPC1 Begins Construction on Kailuan Guye Coal Gangue-Fired Cogeneration Project
Jiangsu Electric Power Construction No.1 Engineering Company kicked off the construction of Kailuan GCL Power Generation Company Limited's 600-megawatt, coal gangue-fired cogeneration project
Released Friday, November 22, 2013
Reports related to this article:
Researched by Industrial Info Resources China (Beijing, China)--Jiangsu Electric Power Construction No.1 Engineering Company (JEPC1) (Nanjing, Jiangsu), a subsidiary of China Energy Engineering Corporation (CEEC) (Beijing), kicked off the construction of Kailuan GCL Power Generation Company Limited's (Tangshan, Hebei) 600-megawatt (MW), coal gangue-fired cogeneration project at the Kailuan Guye Power Plant on November 18, 2013. This is the first thermal power project contracted to JEPC1 in the Hebei province, according to an announcement from the CEEC on the same day.
Kailuan Guye is a pithead power plant located in Tangjiazhuang, Guye District, in Tangshan City, in northern China's Hebei province. The power plant mainly uses low heat-value inferior coals, such as coal gangue, as its fuel in the Kailuan Mining Zone. As a resource comprehensive utilization project, the power plant also will use draining water from Kailuan Coal Mine as its water source.
The project received approval from the National Development and Reform Commission in April 2011. According to the approval, the project will be furnished with two 300-MW, air-cooling, extraction-condensing steam turbine generating units, with two 1,065-ton-per-hour, subcritical, single-reheat, circulating fluidized bed (CFB) boilers. Total investment in the project will be about $500 million.
In April 2013, Kailuan Group (Tangshan, Hebei) and Golden Concord Holdings Limited (Hong Kong) signed a joint venture agreement for the construction of the project. The engineering contract was awarded to North China Power Engineering Company Limited (Beijing).
JEPC1 won the construction and erection bid of the project through public bidding at the end of October 2013. According to the schedule, both units of the project begin operations in the first half of 2015. Upon completion, the project will be able to supply about 3 billion kilowatt-hours of electricity to the grid and provide centralized heating for a total area of 12 million square meters by shutting down 17 small-size, coal-fired boilers within its service area.
View Project Report - 300143183
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our Solutions
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
Latin America Data Center Outlook 2026: Power, Hubs & GrowthPodcast Episode / Oct 9, 2026
-
Food and Beverage CapEx Outlook 2026: Tariffs, AI, AfricaPodcast Episode / Oct 9, 2026
-
North America Refining 2026: New Pipelines to PADD 5Podcast Episode / Oct 2, 2026
-
Biomanufacturing Onshoring 2026: GLP-1, CDMO and ReshoringPodcast Episode / Oct 2, 2026
-
2026 US Data Center Outlook: Power, Land & CoolingPodcast Episode / Sep 18, 2026