Petroleum Refining
IIR Top Refining News Today: March 3rd 2021
Delek US Holdings experienced a fire on February 27 on the 6,000-BBL/d Isomerization 6 unit at its 80,000-BBL/d El Dorado, Arkansas, refinery, while the unit was under planned maintenance
Released Wednesday, March 03, 2021
North America
Delek US Holdings experienced a fire on February 27 on the 6,000-BBL/d Isomerization 6 unit at its 80,000-BBL/d El Dorado, Arkansas, refinery, while the unit was under planned maintenance. The 38-day, plant-wide maintenance turnaround began February 14 and will continue. An investigation into the cause, as well as damage assessment, are ongoing.
Irving Oil remains on schedule for a 60-day planned maintenance turnaround, starting September 16, of six units at its 300,000-BBL/d Saint John, New Brunswick, refinery. Separately, planned maintenance on the 25,000-BBL/d FCCU 25 (old unit) and 8,000-BBL/d SF Alky 32 (old unit), originally scheduled for September 2022, has been moved up to spring 2022.
Delek US Holdings shut down the 25,000-BBL/d FCCU on March 1 due to a leak at its 65,000-BBL/d Big Spring, Texas, refinery. Separately, four units were shut down on February 20, as well as the 22,750-BBL/d Diesel Hydrotreater (ULSD) on February 15.
International
SK Energy Company Limited continues reduced operations at its 840,000-BBL/d Ulsan Complex in South Korea, due to poor economics. The 60,000-BBL/d Crude 1, and three other units, remain de-rated by 15%. The 240,000-BBL/d Crude 4 has been shut down since January 12 and will remain as such until March 17. It will then undergo a 31-day planned maintenance turnaround from March 18 to April 17.
Saras Spa has completed a planned plant-wide shutdown, due to poor economics, of its 300,000-BBL/d Saras Refinery in Italy. The shutdown began in mid-October, and was completed in late February. The refinery has returned to its normal capacity.
PKN Orlen SA continues with a planned maintenance turnaround of the 69,452-BBL/d CDU IV Crude and 65,500-BBL/d VDU IV Vacuum Distillation Unit at its 277,808-BBL/d Plock Refinery in Poland. The units were shut down on January 31, and are tentatively expected to restart by March 12. Meanwhile, a one-month maintenance turnaround of the 69,452-BBL/d CDU II Crude and VDU II Vacuum Distillation Unit is expected to kick off in mid-April.
For more insight contact iirteam@iirenergy.com
www.iirenergy.com
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
Oil Prices Jump as Gloves Come off in Middle EastJuly 13, 2026
-
Middle East Conflict Impacts Global RefiningJuly 13, 2026
PECWeb Global Market Intelligence Platform
Identify opportunities, anticipate change, and execute with confidence. PECWeb connects the industrial intelligence you need, from projects and assets to operational events, all in one platform.
Discover PecwebIndustry Intel
-
European Chemicals and Transport Fuels OutlookPodcast Episode / Jul 10, 2026
-
2026 European Petroleum Refining Project OutlookPodcast Episode / Jun 26, 2026
-
Brazil: Efficiency, Innovation, and Opportunities in the Food & Beverage IndustryPodcast Episode / Jun 12, 2026
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026