Researched by Industrial Info Resources (Sugar Land, Texas)--Oncor Electric Delivery Company (Dallas, Texas) and Brazos Electric Power Cooperative (Waco, Texas) plan to build a 22-mile power transmission project in central Texas at a cost of $32 million. The proposed project would reach completion in 2020.
The 138-kilovolt (kV) Cogdell-Clairemont Transmission Line Project would connect Oncor's existing Cogdell substation in Scurry County and Brazos Electric's Claremont substation in Kent County.
The project includes substation upgrades as well as the construction of the transmission line. Project construction is expected to start in mid-2019, with completion in mid-2020.
The project developers said in a community presentation last summer that assessment of the existing 138-kV facilities serving Kent and Scurry counties has identified the need for improvements in the region. The proposed Cogdell-Clairemont line would strengthen the transmission system in order to improve reliability to existing customers, as well as allow for planned outages for system maintenance and other activities, the developers said.
Oncor serves nearly 10 million customers across Texas, and maintains the largest distribution and transmission system in the state. Brazos Electric is the largest generation and transmission cooperative in the state.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, six offices in North America and 12 international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities. Follow IIR on: Facebook - Twitter - LinkedIn. For more information on our coverage, send inquiries to info@industrialinfo.com or visit us online at http://www.industrialinfo.com.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Learn MoreRelated Articles
-
Dallas-Fort Worth Area is Key U.S. Data Center Destination N...December 11, 2025
-
Texas Utility Oncor Boosts 5-Year Capex to $36 BillionJuly 16, 2025
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Learn MoreIndustry Intel
-
2026 Regional Chemical Processing OutlookOn-Demand Podcast / Mar. 2, 2026
-
From Data to Decisions: How IIR Energy Helps Navigate Market VolatilityOn-Demand Podcast / Nov. 18, 2025
-
Navigating the Hydrogen Horizon: Trends in Blue and Green EnergyOn-Demand Podcast / Nov. 3, 2025
-
ESG Trends & Challenges in Latin AmericaOn-Demand Podcast / Nov. 3, 2025
-
2025 European Transportation & Biofuels Spending OutlookOn-Demand Podcast / Oct. 27, 2025