Adex Mining's $50 Million Restart of New Brunswick Tin Mine on Track with Consultant, Engineering Firm
The Mount Pleasant property includes more than 100 prospective mineral claims covering about 4,000 acres, as well as an additional 1,000 acres of surface rights.
Released Friday, March 21, 2008
Researched by Industrial Info Resources (Sugar Land, Texas)--Thibault & Associates Incorporated (New Maryland, New Brunswick) has been chosen as the consultant for Adex Mining Corporation's (Toronto, Ontario) $50 million restart project for its tin mine in Mount Pleasant, New Brunswick.
In the early 1980s, Billiton Exploration Canada Limited invested more than $150 million to construct the tungsten mine and mill at Mount Pleasant's Firetower Zone (zone two). The mine was operational from 1983 to 1985 and produced 990,200 tons of tungsten ore. Poor economic conditions and a major drop in the price of tungsten led to the mine's closure in 1985. The surface facilities remaining from the mine include ore storage areas, conveyor galleries, warehouse space and office space that are all considered to be in first-rate condition. Because so much of the infrastructure remains, the mine will require a reasonably modest effort and a much more conservative capital investment to bring them up to today's standards. These factors are seen as reason for the reduced overall costs associated with reactivating the mine.
The previous owners of Mount Pleasant started the process of identifying the property's tin and indium deposits (zone one). Those findings produced some impressive results that set the stage for Adex to continue to explore the region. Testing rigs are on-site as the company continues to explore the optimum areas to mine. This area was acquired in 1995 from Piskahegan Resource Limited when Adex began conducting exploration and metallurgical tests on the tin-indium deposits. In 1997, as economic conditions in the mining industry worsened, this part of the property was placed in a care and maintenance phase.
Before the final approvals and permitting is complete, Adex has already taken steps to upgrade the former tailings management area. The company selected Monteith Underground Services Limited (Fredericton, New Brunswick) to oversee the upgrades and repairs needed to get the restart project one step closer to completion. The tailing area upgrades are expected to be finished by the end of the year. The mine restart is not expected to be completed until early 2010.
View Plant Profile - 1029555
View Project Report - 61000069 61000347
Industrial Info Resources (IIR) is a marketing information service specializing in industrial process and energy related industries with products and services ranging from industry news, forecasting, plant and project databases, as well as multimedia advertising campaign assistance.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our SolutionsRelated Articles
-
McEwen to Boost Gold Production Up to 140% by 2030May 12, 2026
-
Ghana Mandates Local Ownership for MiningMay 07, 2026
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Discover Our DatabaseIndustry Intel
-
The Role of Contract Manufacturing in Global Pharma GrowthPodcast Episode / May 8, 2026
-
2026 North American Labor OutlookPodcast Episode / Apr 24, 2026
-
2026 European Metals & Minerals Project Spending OutlookPodcast Episode / Apr 7, 2026
-
The Age of Critical Minerals in the AmericasPodcast Episode / Mar 20, 2026
-
2026 Regional Chemical Processing OutlookPodcast Episode / Mar 6, 2026