Australia's Muja Coal-Fired Power Station Prepares for Major Shutdowns
State-owned energy provider Synergy is preparing for major maintenance outages at its Muja coal-fired power plant in Australia
Released Monday, June 02, 2014
Researched by Industrial Info Resources Australia (Perth, Australia)--State-owned energy provider Synergy (Perth, Australia) is preparing for major maintenance outages at its Muja coal-fired power plant in Australia. The two maintenance outages are scheduled to begin in the second and third quarters of 2014.
The major maintenance shutdown of the 200-megawatt (MW) Unit D7 at Muja is due to begin in June. Following its completion, Synergy will perform a similar outage on Unit D8 in September. Sources at the plant have confirmed that the outage will involve repairs and inspections to the 200-MW Parsons reheat condensing steam turbine, and the 2,379-pound-per-square-inch (PSIG) Omnical supercritical coal-fired boiler.
The maintenance outages on each unit will last for six weeks. Synergy's in-house maintenance team will carry out the maintenance on the balance of plant equipment, while Transfield Worley Power Services Pty Limited (North Sydney, Australia) will act as a major contractor. Transfield has signed a nine-year service agreement to conduct maintenance at the Muja plant.
The 974-MW Muja plant, which is 22 kilometers east of Collie, Western Australia, began operations in 1966 with two 120-MW units. The plant features eight steam turbines, which were built in four stages during 1968 and 1985, with each stage comprising two units. Synergy mothballed the four units at A&B stations in 2010, and performed major refurbishment in association with Inalco Energy as a joint venture partner. The $335 million refurbishment project was heavily funded by the state government. Synergy completed refurbishment of two units at Muja B in the first quarter of 2013.
However, the refurbishment of the other two units, 1 and 2, was halted in June 2013 due to commercial factors. The refurbishment resumed by end of 2013, and was completed in 2014.
View Plant Profile - 1058834
View Project Report - 300075158 300166012
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and 10 international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Explore Our Solutions
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Discover Our DatabaseIndustry Intel
-
2026-2027 Investment Radar for Mexico, Central America & the CaribbeanPodcast Episode / May 29, 2026
-
Innovations Shaping the Next Era of Power GenerationPodcast Episode / May 22, 2026
-
The Role of Contract Manufacturing in Global Pharma GrowthPodcast Episode / May 8, 2026
-
2026 North American Labor OutlookPodcast Episode / Apr 24, 2026
-
2026 European Metals & Minerals Project Spending OutlookPodcast Episode / Apr 7, 2026