Delays in the acquisition of 'right of use' have pushed back the completion of ONGC's Hazira-Dahej pipeline project in Gujarat. The execution of 102-kilometer pipeline project has

Released Tuesday, March 12, 2013

Right-of-Use Hurdle Pushes Back ONGC's Hazira-Dahej Pipeline Project

Reports related to this article:


Researched by Industrial Info Resources (Delhi, India)--Delays in the acquisition of "right of use" (RoU) have pushed back the completion of Oil and Natural Gas Corporation's (BSE:500312) (ONGC) (Dehradun, Uttarakhand) Hazira-Dahej pipeline project in Gujarat. The execution of 102-kilometer pipeline project has been held up for about seven months due to a logjam, which is inherent to pipeline projects in India. A slew of vital crude and petroleum-product pipeline projects that were identified for implementation in recent times have been stalled due to RoU hurdles.

The $35 million pipeline project is now likely to be on-stream by August 2013, as opposed to its original completion schedule of January 2013. The construction of the pipeline is running behind schedule due to obstructions caused by local residents in handing over the RoU to ONGC. The pipeline is passing through 47 villages in the state of Gujarat. Reportedly, farmers and landowners were demanding higher compensation for giving the RoU to ONGC.

In December 2011, Punj Lloyd Engineering Limited (BSE:532693) (Gurgaon, Haryana) was awarded the contract for laying the pipeline, and construction for the project began in April 2012. The feeder line will supply naphtha from ONGC's Hazira gas-processing facility to its upcoming petrochemical complex at Dahej.

The Hazira Plant is the largest gas-processing complex in India, with a designed capacity of 40.6 million standard cubic meters per day (MMSCMD) of sour natural gas and associated sour condensate. The plant was commissioned in December 1987, with a gas-based liquid petroleum gas (LPG) plant with a capacity of 5 million standard cubic feet per day, which was then scaled up through four subsequent expansions.

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 98 + 0?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

Industrial Project Opportunity Database and Project Leads

Get access to verified capital and maintenance project leads to power your growth.

Discover Our Database