Shannon LNG Delays Construction Date, Remains Committed to Constructing Irish LNG-Receiving Terminal

Shannon LNG Limited (Dublin, Ireland) is planning to construct a new liquefied natural gas (LNG) receiving and re-gasification terminal in Ireland. Shannon LNG is a wholly owned ...

Released Tuesday, December 23, 2008


Researched by Industrial Info Resources (Sugar Land, Texas)--Shannon LNG Limited (Dublin, Ireland) is planning to construct a new liquefied natural gas (LNG) receiving and re-gasification terminal in Ireland. Shannon LNG is a wholly owned subsidiary of Hess LNG Limited (New York, New York), which is a joint venture of Poten & Partners Incorporated (New York, New York) and Hess Corporation (NYSE:HES) (New York, New York). The proposed LNG terminal will be located on the Shannon Estuary with its deep water channel approximately 4.5 kilometers from Tarbert and 3.5 kilometers from Ballylongford on a 280-acre site. Originally, the $800 million terminal was scheduled for construction in 2009, but the permitting process and current global economics have pushed the construction start to late 2010 or early 2011.

Shannon LNG has received permits for the LNG terminal and is studying the permits required to construct the 30-kilometer, 30-inch-diameter natural gas pipeline to tie the LNG terminal into the grid. The permitted Shannon LNG terminal will have an initial send-out capacity of 400 million cubic feet per day of natural gas, with a peak gas send-out level of 600 million cubic feet per day. To support this send out capacity, Shannon LNG will construct two of the permitted 200,000-cubic-meter LNG storage tanks. Because of the channel's deep water and the design of the Shannon LNG terminal, LNG Carriers designed with a cargo capacity of up to 265,000 cubic meters of LNG will be able to discharge their cargos at the terminal. Up to 125 of these large LNG carriers could discharge cargos each year at the site.

Shannon LNG Limited expects to receive permitting for the natural gas pipeline portion of the project and begin the front-end engineering and design (FEED) phase of the LNG terminal in late 2009. Construction on the Shannon LNG Terminal is expected to begin in late 2010 or early 2011 and take up to three years to construct. Construction is expected to create up to 600 construction jobs and the Shannon LNG project is expected to create 50-60 new permanent jobs when completed and operating.

Shannon LNG's project is just one of approximately 35 new LNG terminals currently being developed in Europe, six of which are presently under construction. Europe seems to be experiencing an extensive expansion of LNG facilities similar to what happened in North America beginning in late 2004.

View Plant Profile - 1071943
View Project Report - 80300080 80300090

Industrial Info Resources (IIR) is a marketing information service specializing in industrial process, energy and financial related markets with products and services ranging from industry news, analytics, forecasting, plant and project databases, as well as multimedia services.
/news/article.jsp false
Share This Article
Want More IIR News Intelligence?

Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 33 + 0?
Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Learn More
Industrial Project Opportunity Database and Project Leads

Get access to verified capital and maintenance project leads to power your growth.

Learn More
Industry Intel


Explore Our Coverage

Industries


  • Electric Power
  • Terminals
  • Pipelines
  • Production
  • Alternative Fuels
  • Petroleum Refining
  • Chemical Processing
  • Metals & Minerals
  • Pulp, Paper & Wood
  • Food & Beverage
  • Industrial Manufacturing
  • Pharmaceutical & Biotech

Trending Sectors


  • Data Centers
  • Semiconductors
  • Battery Supply Chain
  • Packaging
  • Nuclear Power
  • LNG