Power
Environmental Report for Huadian Ankang Coal-Fired Project Receives Approval
The environment impact assessment report for Huadian Grassroot Ankang's 2,000-megawatt coal-fired power plant project recently received approval from the Ministry of Environment Protection
Released Wednesday, December 18, 2013
Reports related to this article:
Project(s): View 1 related project in PECWeb
Plant(s): View 1 related plant in PECWeb
Researched by Industrial Info Resources China (Beijing, China)--The environment impact assessment (EIA) report for Huadian Grassroot Ankang's 2,000-megawatt (MW) coal-fired power plant project recently received approval from the Ministry of Environment Protection (MEP), according to an announcement from the MEP on December 4, 2013.
The Huadian Ankang Coal-fired Power Plant, located in Hechi Town, Shiquan County of Ankang City, in northwest China's Shaanxi province, is a key energy construction project in both the nation's 12th Five-Year (2011-15) Development Plan and the Shaanxi Provincial Development Plan. The project is jointly invested by Huadian Shaanxi Energy Company Limited (Xian, Shaanxi) and Chemical Group Company Limited (Xian, Shaanxi). Northwest Electric Power Design Institute (NWEPDI) (Xian, Shaanxi) is responsible for the design and engineering of the project.
According to the approval, the project will be furnished with two 1,000-MW, ultra-supercritical, coal-fired units, together with associated environmental protection facilities in Phase I, with a total investment of about $1.3 billion. The project will use the surface water from Xihe Reservoir on the mainstream of Hanjiang River as its water supply source. It also will use coal produced from Binchang Mining Zone, mixed with some local coal gangue, as its fuel. The project will adopt high-efficiency electrostatic dust remover; low nitrogen oxide burner; selective catalyst reduction (SCR) for nitrogen oxide control; wet-method flue gas desulfurization; and a 240-meter-high chimney for the emission control of air pollutants.
The project received preliminary approval from the National Development and Reform Commission (NDRC) to begin pre-stage preparation in May 2012. Site preparation of the project kicked off in August 2012.
Presently, the government of Ankang City and China Huadian Corporation are working closely in getting final approval for the project. According to the schedule, both units of the project will begin operations in 2015. Upon completion, the electricity generated from the project will be directly transmitted to the Chongqing grid.
View Project Report - 88001581
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Learn MoreRelated Articles
-
Site Preparation for China Huadian's Ankang Coal-Fired Power...September 06, 2012
-
Today's Chemical Processing Hotline HeadlinesJune 01, 2023
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Learn MoreIndustry Intel
-
2026 North American Labor OutlookPodcast Episode / Apr 24, 2026
-
2026 European Metals & Minerals Project Spending OutlookPodcast Episode / Apr 7, 2026
-
The Age of Critical Minerals in the AmericasPodcast Episode / Mar 20, 2026
-
2026 Regional Chemical Processing OutlookPodcast Episode / Mar 6, 2026
-
From Data to Decisions: How IIR Energy Helps Navigate Market VolatilityPodcast Episode / Nov 21, 2025