Duke Energy Kentucky took 648.4 megawatts (MW) offline from the East Bend 02 unit, on January 25, at its East Bend Power Station #2 in Kentucky due to multiple repairs to boiler tube leaks and the clearing of a boiler slag clog. The unit is operating at 0%, and this event will end February 14 (originally scheduled for January 31).