Marathon remains on schedule to conduct a plant-wide maintenance turnaround in early January next year at its 103,500-BBL/d Wilmington, California, refinery. Units involved include the Lone Crude and 41,000-BBL/d Delayed Coker. Calumet Lubricants will begin out procedures today, October 18, for a plant-wide maintenance turnaround at its 60,000-BBL/d Shreveport, Louisiana, refinery. The first maintenance day will be on Monday, October 21. The event is expected to last about 35 days and will be completed around November 21.