Exelon Generation Company LLC took 204.12 megawatts (MW) offline from the Limerick 01 unit, on March 5, at its Limerick Nuclear Power Station in Pennsylvania. The unit is operating at 82% and coasting down for a refueling outage on March 29.
NextEra Energy Point Beach LLC took 42 MW offline from the Point Beach O2 unit, today, March 10, at its Point Beach Nuclear Power Station in Wisconsin. The unit is running at 93% and coasting down for a refueling outage on March 14.
OG&E Electric Services took the Oklahoma 01 CT/HRSG and Oklahoma Cogen 01 ST units' full capacity offline on February 7 at its Frontier Power Plant in Oklahoma; the units were tripped offline due to an O2 housing failure.