NEW DELHI--September 26, 2025--Researched by Industrial Info Resources (Sugar Land, Texas)--The Indian government is preparing to rebid nearly 40 gigawatts (GW) of stalled solar and wind projects that have failed to progress due to the absence of power purchase agreements (PPAs). Originally awarded through competitive tenders, these projects never moved beyond tariff discovery. Without firm offtake agreements from state distribution companies, developers have been unable to secure financing, leaving large volumes of capacity idle and slowing India's renewable pipeline.